Differences between revisions 136 and 244 (spanning 108 versions)
Revision 136 as of 2017-11-10 09:12:52
Size: 6371
Comment:
Revision 244 as of 2018-01-12 09:24:04
Size: 8383
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
=== Phase1 ===
=== Phase2 ===
 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
Line 11: Line 11:
2017/11/8 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171106.png||width=1200}}
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 19: Line 28:
 * 下げ振り測定
  * 11/9 *木村、荒木、沢田@IYV, IYC、荒木
  .

 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
Line 49: Line 41:
 * 回路: 霜出、上泉  * 回路: 上泉、霜出
Line 65: Line 57:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 68: Line 60:
2017/11/10(Fri) 2017/1/12(Fri.)
Line 70: Line 62:
  * 作業
   * 下げ振り測定
    * IYCでの下げ振り測定が完了。下げ振り中心とビーム中心を比較。-X側に8mm程度ずれていた。高さはほぼぴったり。測定後IYCとBSの間のGVを閉めたので、今日真空引きを始める予定。
    * IXCの真空槽の高さが4mm高かった。
 * Remote participants by educe: None
Line 75: Line 64:
   * 防振関連
    * IO chassisの電源断でPR3のスリップが起きた模様。pitchにミスアラインが起きた。どこがスリップしたかはまだわかっていない。
    * BSのオフセットリリース及びMatrixの設定など。本日も引き続き。カバーをしたが、まだ揺れている。
 * Affect of short power failure
  * VIS
   * EX のポラリティーが反転していた。瞬停と関係あるかは不明。
Line 79: Line 68:
  * 計算機関連
   * k1immtで使っていた光ファイバーケーブルは新しいラックのところまで来た。来週引き続き。
  * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
   * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.
Line 82: Line 71:
 * Daily
  * 作業人員(*:責任者)
   * VIS: Mark, Enzo, 神津
  * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.
Line 86: Line 73:
  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。
 * Report of work (*:responsible person)
  * Alignment: *Izumi
   * X-armまでリカバーした。
   * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
    * GASは真空槽を開けずに直せる範囲を超えている模様。
    * PR3で100uradのオーダーでずれていた。
    * Oplevの範囲をすでに超えてしまっている。
Line 91: Line 82:
  * PLC at Yend: Aso
   * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。

  * Marionet Oplev: Akutsu
   * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。


 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。

  * Marionet Oplev: Akutsu
   * QPDの信号を確認する予定。

 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F
Line 92: Line 101:
  * 11/6の週
   * フロントの下げ振りが11/8-9でその期間はビームを上流で止めることになる。その後もPR系の測定が終わるまではビームはIFIで止める。
  * 11/13の週
   * PR系の位置測定。ただし月曜は拡大チーフ会議などがあり、作業はない見込み。
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.
Line 97: Line 105:
 * 問題点など
  * コーチフィルターが不調。
  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.

  * Week of 1/22
   * 1/24,25 leak check.

  * Week of 1/29
   * 1/29 Cooling start

 * Issues
   * EX のポラリティーが反転していた。回路の問題か?
   * 真空曹を開けてPR2とPR3を直すかどうか。
Line 110: Line 129:
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 122: Line 146:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/10 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/12(Fri.)

  • Remote participants by educe: None
  • Affect of short power failure
    • VIS
      • EX のポラリティーが反転していた。瞬停と関係あるかは不明。
    • IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
      • One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.
    • DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.
  • Report of work (*:responsible person)
    • Alignment: *Izumi
      • X-armまでリカバーした。
      • 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
        • GASは真空槽を開けずに直せる範囲を超えている模様。
        • PR3で100uradのオーダーでずれていた。
        • Oplevの範囲をすでに超えてしまっている。
    • PLC at Yend: Aso
      • 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。
    • Marionet Oplev: Akutsu
      • Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
    • Marionet Oplev: Akutsu
      • QPDの信号を確認する予定。
  • Laser hazard area
    • Behind of BS and SR line and Yend 1F
  • Weekly
    • Week of 1/8
      • 1/11, 12: Re-alignment for IFO.
      • 1/13, 14: Damping for ETMY.
    • Week of 1/15
      • IOO works.
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues
    • EX のポラリティーが反転していた。回路の問題か?
    • 真空曹を開けてPR2とPR3を直すかどうか。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members