6135
Comment:
|
6959
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
* [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Commissioning/Phase1/Task|Phase1]] ==== Stage 1 ==== ==== Stage 2 ==== * Target * Alignment of ETMy * Preparation * Oplev * Actuator * EYCのTypeAとPayload接続完了 ==== Stage 3 ==== * Alignment of ETMx * Locking of MI with Cryogenic ETMy with Calibrated sensitivity curve ==== Stage 4 ==== * Locking of MI in vacuum with cryogenic ETMx/y with data stored ==== Test run ==== * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Commissioning/Phase2/Task|Phase2]] |
* [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] |
Line 30: | Line 11: |
2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
Line 36: | Line 17: |
* 責任者 | * *: responsible person * Re alignment * 1/11 *Izumi, Nagano, Shimoda * 1/12 *Izumi, Nagano, Shimoda * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 38: | Line 29: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/13 *新井、正田(午後~) * 11/14 *新井、正田 * 11/15 *木村、沢田、新井、正田(蓋閉め) * 11/16 *木村、沢田、新井、正田(蓋閉め) * 11/17 *新井、正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
|
Line 80: | Line 58: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 83: | Line 61: |
2017/11/14(Tue.) | 2017/1/10(Wed.) |
Line 85: | Line 63: |
* Daily * 作業 * PR系測定 * 昨日に引き続き、オプティカルベンチの高さ合わせなどを継続中。 * 昨日COACHフィルターをオンにしたため、振り子類が大きく揺れている。 * 測定機器(FARO)が今日届くので、届き次第測定開始。 |
* 12時半よりファン小屋で真空と低温の細かい打ち合わせ。 |
Line 92: | Line 65: |
* 計算機関連 * k1prmのケーブル接続をする。 |
* Remote participants by educe: None |
Line 95: | Line 67: |
* Commission workの準備: QPDの設置など | * Report of work (*:responsible person) |
Line 97: | Line 69: |
* 作業人員(*:責任者) * PR系測定: *正田、新井、飯田 * 計算機: 宮川、三代 * Laser hazard * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはIFIより奥。 |
* Work plan (*:responsible person) |
Line 106: | Line 72: |
* Laser hazard * センターはIMM奥がハザードエリア。 |
|
Line 107: | Line 76: |
* 11/13の週 * PR系の位置測定。 |
* Week of 1/8 * vacuum meeting 12:30 on 1/10, at fan hut. * Re-alignment for IFO on 1/11, 12. * Damping for ETMY on 1/13, 14. |
Line 110: | Line 81: |
* 問題点など | * Week of 1/15 * IOO works. * Pump down, leak check in the later of this week. * Issues |
Line 122: | Line 98: |
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
|
Line 134: | Line 115: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/10 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/11 *Izumi, Nagano, Shimoda
- 1/12 *Izumi, Nagano, Shimoda
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/10(Wed.)
- 12時半よりファン小屋で真空と低温の細かい打ち合わせ。
- Remote participants by educe: None
- Report of work (*:responsible person)
- Work plan (*:responsible person)
- Laser hazard
- センターはIMM奥がハザードエリア。
- Weekly
- Week of 1/8
- vacuum meeting 12:30 on 1/10, at fan hut.
- Re-alignment for IFO on 1/11, 12.
- Damping for ETMY on 1/13, 14.
- Week of 1/15
- IOO works.
- Pump down, leak check in the later of this week.
- Week of 1/8
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools