Differences between revisions 146 and 231 (spanning 85 versions)
Revision 146 as of 2017-11-14 12:30:04
Size: 5895
Comment:
Revision 231 as of 2018-01-05 13:52:23
Size: 6544
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/1/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/13 *新井、正田(午後~)
  * 11/14 *新井、正田
  * 11/15 *木村、沢田、新井、正田(蓋閉め)
  * 11/16 *木村、沢田、新井、正田(蓋閉め)
  * 11/17 *新井、正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
Line 61: Line 48:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 64: Line 51:
2017/11/14(Tue.) 2017/1/5(Fri.)
Line 66: Line 53:
 * Daily
  * 作業
   * PR系測定
    * 昨日に引き続き、オプティカルベンチの高さ合わせなどを継続中。
    * 昨日COACHフィルターをオンにしたため、振り子類が大きく揺れている。
    * 測定機器(FARO)が今日届くので、届き次第測定開始。
 * Remote participants by educe: None
Line 73: Line 55:
  * 計算機関連
   * k1prmのケーブル接続をする。

  * Commission workの準備: QPDの設置など

  * 作業人員(*:責任者)
   * PR系測定: *正田、新井、飯田
   * 計算機: 宮川、三代

  * Laser hazard
   * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
   * ハザードエリアはIFIより奥。
 * 停電からの復帰関連
  * DGS: PR3も復帰した。DACが一枚不調だった。k1imcのDACを一枚抜いた。入れ替えは直っているはず。
  * IOO: MCまで復帰。回路も特に問題ない。
  * 真空: MC再起動。腕はまだ(来週)。
  * Tcam: 2秒間隔で見えるようになった。
Line 87: Line 62:
 * Report of work (*:responsible person)
  * Type A: Remoteで測定していた模様。

 * Work plan (*:responsible person)


 * Laser hazard
  * センターはIMM奥がハザードエリア。
Line 88: Line 72:
  * 11/13の週
   * PR系の位置測定。
  * Week of 1/5
Line 91: Line 74:
 * 問題点など   * Week of 1/8
   * meeting
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.

  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.

 * Issues
  * Remoteでの接続が遅い。VPNかk1gateのDNSか?
Line 103: Line 97:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 116: Line 113:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/5 updated KAGRA/Commissioning/Commissioning_schedule_20180109.png


Working people assignment

* 責任者



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/5(Fri.)

  • Remote participants by educe: None
  • 停電からの復帰関連
    • DGS: PR3も復帰した。DACが一枚不調だった。k1imcのDACを一枚抜いた。入れ替えは直っているはず。
    • IOO: MCまで復帰。回路も特に問題ない。
    • 真空: MC再起動。腕はまだ(来週)。
    • Tcam: 2秒間隔で見えるようになった。
  • Report of work (*:responsible person)
    • Type A: Remoteで測定していた模様。
  • Work plan (*:responsible person)
  • Laser hazard
    • センターはIMM奥がハザードエリア。
  • Weekly
    • Week of 1/5
    • Week of 1/8
      • meeting
      • Re-alignment for IFO on 1/11, 12.
      • Damping for ETMY on 1/13, 14.
    • Week of 1/15
      • IOO works.
      • Pump down, leak check in the later of this week.
  • Issues
    • Remoteでの接続が遅い。VPNかk1gateのDNSか?

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)