6212
Comment:
|
8718
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} |
2017/1/18 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Re alignment * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 19: | Line 28: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
|
Line 58: | Line 57: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 61: | Line 60: |
2017/11/17(Fri.) | 2017/1/18(Thur.) |
Line 63: | Line 62: |
* Daily * 作業 * PR系測定 * PR2タンク上部を閉めた。 * タンクO-ringを閉めるときに、PR2のOplevがずれてしまった可能性が高い。 * FAROのPR2の測定結果: -Xに9mm -Zに5mmずれていることが判明。 * 本日PR3の測定をする。来週続いてPRMも測定する。 |
* Remote participants by educe: None * Report of work (*:responsible person) * Vacuum * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY. * IOO: *Kokeyama * 1WがMCに入った。 * Alignment: *Izumi * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。 * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。 * ETMYからの戻り光をリサージュで一晩降ったが見つかっていない。スリットを再び入れる予定。 * Work plan (*:responsible person) * Alignment: *Izumi * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。 * 11時頃まで作業のためにレーザーハザードは全域。11時から通常のIMMより手前に戻す。 |
Line 72: | Line 82: |
* 計算機関連 * k1prmのケーブル接続を引き続き継続。 |
* 真空引きの最終判断は月曜日にする。 * チェックリスト最終確認。 * φ800フランジを閉める。 * Laser hazard: All area until 11AM, then changed to ipstream of IMM line. Hayakawa will change the border by 11AM. * Weekly * Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * Week of 1/22 * 1/23: Pump down. * 1/29,30 leak check. * Week of 1/29 * 1/29 Cooling start |
Line 76: | Line 103: |
* 作業人員(*:責任者) * PR系測定: *正田、新井、木村、澤田 * 計算機: 宮川、山本 * Laser hazard * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはIFIより奥。 * Weekly * 11/13の週 * PR系の位置測定。 * 11/20の週 * PR系の位置測定。 * Watch dogのテストとPRMのリリース。 * 問題点など * ケーブル、作業スペースなどの環境が恐ろしく悪い。 * PR2、3のアラインメントにメインビームが必要。CRYは今週はメンビームは出して欲しくない。 * フタしめの、ボルトのありかがわからない(木村) -> 内山 |
* Issues * Network cableの整理 * Cryostatがタッチしている可能性あり。 * ビームアラインメントの最終確認が時間的にぎりぎり。 |
Line 107: | Line 118: |
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || | ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
Line 120: | Line 136: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/18 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/18(Thur.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Vacuum
- Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
- IOO: *Kokeyama
- 1WがMCに入った。
- Alignment: *Izumi
- ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
- Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
- ETMYからの戻り光をリサージュで一晩降ったが見つかっていない。スリットを再び入れる予定。
- Vacuum
- Work plan (*:responsible person)
- Alignment: *Izumi
- EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
- 11時頃まで作業のためにレーザーハザードは全域。11時から通常のIMMより手前に戻す。
- 真空引きの最終判断は月曜日にする。
- チェックリスト最終確認。
- φ800フランジを閉める。
- Alignment: *Izumi
- Laser hazard: All area until 11AM, then changed to ipstream of IMM line. Hayakawa will change the border by 11AM.
- Weekly
- Week of 1/15
- 1/15~ baffle PD installation
- 1/16~ IOO works.
- 1/17: Vacuum check meeting
- Week of 1/22
- 1/23: Pump down.
- 1/29,30 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/15
- Issues
- Network cableの整理
- Cryostatがタッチしている可能性あり。
- ビームアラインメントの最終確認が時間的にぎりぎり。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools