Line 11: | Line 11: |
2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} |
2017/1/16 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Re alignment * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 19: | Line 28: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
|
Line 58: | Line 57: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 61: | Line 60: |
2017/11/22(Wed.) | 2017/1/18(Thur.) |
Line 63: | Line 62: |
* Daily * 作業 * Type A: 復帰した。 * IOO: PSLとMCともに光軸ズレがありそう。今日もう一度確認する。 * 計算機: ほぼ復帰。k1bsとk1ey1, k1ex0, k1ey0に少しトラブルあり。 * Type Bp: PR系は信号は来ている。PR2のAAフィルターが調子が悪いので交換。PRMのリリースをしたがぶつかっている様子。 * タンクからサテライトボックスまでのD-SUBケーブルが一つダメになっている。 * PR2のBIOを一枚増やした。カードの認識がバラバラ。インプットとアウトプットさえバラバラ。 * 真空: MC復帰した。Xarm復帰した。Yarmを今日か明日復帰する。 * Yendピット内の水がまだ冠水中。今日シートをかぶせて作業を再開。 * MCFの前のGreenとPOP用光学定盤を移動させたい。 * 12時からeZuceでiKAGRAからの引き継ぎ会議。 |
* Remote participants by educe: None * Report of work (*:responsible person) * Alignment: *Izumi * EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。 * ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。 * CryoPayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。 * IOO * PSL上のパワーを変更して、メインパワーを1Wまで上げた。実際には干渉計直前で蹴っているので、干渉計側には今まで通り100mW程度が入っている。メインパワーの変動が数十%と大きくなってしまっている。今の所変動の原因は不明。 * Work plan (*:responsible person) * Alignment: *Izumi * BSからETMYにビームを飛ばしたが、まだ見えていない。ゲインが500倍くらい低かったせい。午後3、4時頃から、再度ゲインを上げて試す。 * CryoPayloadのVisual inspection. * φ800フランジは今日は開けておく。明日しめる。 * IOO * 1WをMCに入れる * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment. * Weekly * Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. * Week of 1/29 * 1/29 Cooling start |
Line 77: | Line 99: |
停電のため報告、作業予定特になし。 * 作業人員(*:責任者) * Type Bp: *正田、和泉、田中 * MIF/AOS: *道村、阿久津、中田 * Laser hazard * IFIより奥。 * Weekly * 11/20の週 * 昨日停電復帰。 * PR系の位置測定。 * Watch dogのテストとPRMのリリース。 * 問題点など * PR2、3のアラインメントにメインビームが必要。CRYは今週はメインビームは出して欲しくない。 * PRMがリリースしたがぶつかっている様子。 * D-SUBケーブルがおかしくなったものが出た。 |
* Issues * Network cableの整理 |
Line 109: | Line 112: |
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || | ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
Line 122: | Line 129: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/16 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/18(Thur.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Alignment: *Izumi
- EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
- ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
CryoPayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。
- Alignment: *Izumi
- IOO
- PSL上のパワーを変更して、メインパワーを1Wまで上げた。実際には干渉計直前で蹴っているので、干渉計側には今まで通り100mW程度が入っている。メインパワーの変動が数十%と大きくなってしまっている。今の所変動の原因は不明。
- Work plan (*:responsible person)
- Alignment: *Izumi
- BSからETMYにビームを飛ばしたが、まだ見えていない。ゲインが500倍くらい低かったせい。午後3、4時頃から、再度ゲインを上げて試す。
CryoPayloadのVisual inspection.
- φ800フランジは今日は開けておく。明日しめる。
- IOO
- 1WをMCに入れる
- Alignment: *Izumi
- Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.
- Weekly
- Week of 1/15
- 1/15~ baffle PD installation
- 1/16~ IOO works.
- 1/17: Vacuum check meeting
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/15
- Issues
- Network cableの整理
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools