Line 11: | Line 11: |
2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} |
2017/1/18 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Re alignment * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 19: | Line 28: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * |
|
Line 58: | Line 57: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 61: | Line 60: |
2017/11/27(Mon.) | 2017/1/19(Thur.) |
Line 63: | Line 62: |
* Daily * 作業 * Type Bp: インナーフレームの足が浮いているので締め直す必要がある。 * 今日、明日でミラプロに頼んで締め直しをする。 * PRMのリリースはビームのアラインメントが終わってから。 * WS * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。 * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。 * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。 |
* Remote participants by educe: None * Report of work (*:responsible person) * Vacuum * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY. * IOO: *Kokeyama * 1WがMCに入った。 * Alignment: *Izumi * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。 * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。 * ETMYからの戻り光をリサージュで一晩降ったが見つかっていない。スリットを再び入れる予定。 * Work plan (*:responsible person) * Alignment: *Izumi * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。 * 11時頃からレーザーハザードを全域に変更してアラインメント作業。 |
Line 74: | Line 82: |
* 作業人員(*:責任者) * WS: *麻生、苔山、宮川 + 20名程度(見学) |
* 真空引きの最終判断は月曜日にする。 * チェックリスト最終確認。 * φ800フランジを閉める。 |
Line 77: | Line 86: |
* Laser hazard * 今週はSRラインより奥。 |
* Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM. |
Line 81: | Line 90: |
* 11/27の週 * Commissioning Work Shop(11/27-12/1) * PRMの締め直し。 * メインビームの再アラインメント。 |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting |
Line 86: | Line 95: |
* 12/4の週 * Type Aダンピングテスト。 * 12/11の週 * ETMYからの戻り光確認。 * 12/18EYC閉止。 |
* Week of 1/22 * 1/23: Pump down. * 1/24: Turbo pump on. * Week of 1/29 * 1/29,30 leak check. * 1/31? Cooling start. |
Line 93: | Line 104: |
* 問題点など * PRMの足が浮いている。 * D-SUBケーブルがおかしくなったものが出た。 |
* Issues * Network cableの整理 |
Line 108: | Line 117: |
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || | ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
Line 121: | Line 135: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/18 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/19(Thur.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Vacuum
- Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
- IOO: *Kokeyama
- 1WがMCに入った。
- Alignment: *Izumi
- ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
- Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
- ETMYからの戻り光をリサージュで一晩降ったが見つかっていない。スリットを再び入れる予定。
- Vacuum
- Work plan (*:responsible person)
- Alignment: *Izumi
- EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
- 11時頃からレーザーハザードを全域に変更してアラインメント作業。
- 真空引きの最終判断は月曜日にする。
- チェックリスト最終確認。
- φ800フランジを閉める。
- Alignment: *Izumi
- Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM.
- Weekly
- Week of 1/15
- 1/15~ baffle PD installation
- 1/16~ IOO works.
- 1/17: Vacuum check meeting
- Week of 1/22
- 1/23: Pump down.
- 1/24: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- 1/31? Cooling start.
- Week of 1/15
- Issues
- Network cableの整理
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)