Differences between revisions 164 and 253 (spanning 89 versions)
Revision 164 as of 2017-11-27 09:18:32
Size: 6299
Comment:
Revision 253 as of 2018-01-17 12:21:57
Size: 7858
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/1/16 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 19: Line 28:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *
Line 58: Line 57:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 61: Line 60:
2017/11/27(Mon.) 2017/1/17(Wed.)
Line 63: Line 62:
 * Daily
  * 作業
   * Type Bp: インナーフレームの足が浮いているので締め直す必要がある。
    * 今日、明日でミラプロに頼んで締め直しをする。
    * PRMのリリースはビームのアラインメントが終わってから。
   * WS
    * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。
    * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。
   * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。
 * Remote participants by educe: None

 * Report of work (*:responsible person)
  * Alignment: *Izumi
   * Buffle PDがETMYにインストールされた。真空槽内はケーブリングも含めて完了。
   * 読み出し回路を用意している。ケーブルなどと合わせてほぼ準備が整った。計算機側の準備もOK。接続を待つのみ。

 * IOO
  * PSL上のパワーを変更して、メインパワーを1Wまで上げた。実際には干渉計直前で蹴っているので、干渉計側には今まで通り100mW程度が入っている。メインパワーの変動が数十%と大きくなってしまっている。今の所変動の原因は不明。

 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * 午前中EYでの回路接続。夕方から全域をハザートエリアにして、アラインメント作業。

 
 * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.

 * Weekly
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
   * 1/19: Pump down.

  * Week of 1/22
   * 1/24,25 leak check.

  * Week of 1/29
   * 1/29 Cooling start
Line 74: Line 93:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)

  * Laser hazard
   * 今週はSRラインより奥。

 * Weekly
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直し。
   * メインビームの再アラインメント。

  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。


 * 問題点など
  * PRMの足が浮いている。
  * D-SUBケーブルがおかしくなったものが出た。
 * Issues
  * Network cableの整理
Line 108: Line 106:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 121: Line 123:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/16 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/17(Wed.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • Alignment: *Izumi
      • Buffle PDがETMYにインストールされた。真空槽内はケーブリングも含めて完了。
      • 読み出し回路を用意している。ケーブルなどと合わせてほぼ準備が整った。計算機側の準備もOK。接続を待つのみ。
  • IOO
    • PSL上のパワーを変更して、メインパワーを1Wまで上げた。実際には干渉計直前で蹴っているので、干渉計側には今まで通り100mW程度が入っている。メインパワーの変動が数十%と大きくなってしまっている。今の所変動の原因は不明。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • 午前中EYでの回路接続。夕方から全域をハザートエリアにして、アラインメント作業。
  • Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.
  • Weekly
    • Week of 1/15
      • 1/15~ baffle PD installation
      • 1/16~ IOO works.
      • 1/17: Vacuum check meeting
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues
    • Network cableの整理

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings