6429
Comment:
|
8012
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) * Beam leading to REFP port * *Izumi |
Line 19: | Line 25: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * ・PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。 |
|
Line 60: | Line 54: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 63: | Line 57: |
2017/11/27(Mon.) | 2017/1/23(Tue.) |
Line 65: | Line 59: |
* Daily * 作業 * Type Bp: * インナーフレームの足が浮いているので締め直す必要がある。今日、明日でミラプロに頼んで締め直しをする。 * PRMのリリースはビームのアラインメントと並行に進める。今週後半か。 * WS * 10時頃海外組が到着。10時半スタート。午後に見学、夕方から計画検討など。 * 梱包を解くなどの準備があるので午後見学と同じ時間に見学の必要のない人は手伝ってください。 * メインビームのアラインメントを水曜以降にする。PRMのリリースも並行してできそう。 |
* Remote participants by educe: None * Report of work (*:responsible person) * IOO: 苔山 * 精密空調が入って、温度が安定した。 * Vacuum * Oplevがヒートリンクで遮られていた。 * Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。 * 再度戻り光も確認した。 * 真空引きの準備がほぼ完了。 * BS:神津、Enzo * リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。 |
Line 76: | Line 75: |
* 作業人員(*:責任者) * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業) |
* Work plan (*:responsible person) * Vacuum * 昨日午後から延期になって、本日朝真空引き予定 * ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川 * コントロールルーム: 和泉、奥富 * Check listによる最終確認 |
Line 79: | Line 82: |
* Laser hazard * 今日明日はIMMTより奥、水曜からSRラインより奥。 |
* Laser hazard: 今日は午前はPSLのみ。午後からIMMT。 |
Line 83: | Line 85: |
* 11/27の週 * Commissioning Work Shop(11/27-12/1) * PRMの締め直し。 * メインビームの再アラインメント。 |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
Line 88: | Line 89: |
* 12/4の週 * Type Aダンピングテスト。 * 12/11の週 * ETMYからの戻り光確認。 * 12/18EYC閉止。 |
* Week of 1/29 * 1/29,30 leak check. * Week of 2/5 * 2/5 Cooling start. |
Line 95: | Line 96: |
* 問題点など * PRMの足が浮いている。 * D-SUBケーブルがおかしくなったものが出た。 |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 110: | Line 110: |
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || | ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
Line 116: | Line 121: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 123: | Line 128: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/23(Tue.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- IOO: 苔山
- 精密空調が入って、温度が安定した。
- Vacuum
- Oplevがヒートリンクで遮られていた。
- Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。
- 再度戻り光も確認した。
- 真空引きの準備がほぼ完了。
BS:神津、Enzo
- リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。
- IOO: 苔山
- Work plan (*:responsible person)
- Vacuum
- 昨日午後から延期になって、本日朝真空引き予定
- ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川
- コントロールルーム: 和泉、奥富
- Check listによる最終確認
- 昨日午後から延期になって、本日朝真空引き予定
- Vacuum
- Laser hazard: 今日は午前はPSLのみ。午後からIMMT。
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools