Line 11: Line 11:
2017/11/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}}
2017/1/16 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 19: Line 28:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
Line 60: Line 57:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 60:
2017/11/28(Tue.) 2017/1/18(Thur.)
Line 65: Line 62:
 * Daily
  * 作業
   * Type Bp:
    * インナーフレームの足が浮いているのでシムを入れて、傾きを補正して締め直したす。水平になっているはず。
    * PRMを今日リリースする予定。
   * アラインメント
    * PSLQPDでピッチ方向にずれ、MCTのQPDにヨー方向にずれがあった。IMMT1、2のアラインメントを取り直して、PR真空曹のフランジのセンターには当たった。
    * メインビームのアラインメントは明日の水曜以降に続ける。
   * WS
    * 昨日夕方から一部実際の作業が始まっている。
    * 物の準備はだいたい完了。一部足りないものを持ち込むなどの作業がある。
 * Remote participants by educe: None

 * Report of work (*:responsible person)
  * Alignment: *Izumi
   * EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
   * ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
   * CryoPayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。

 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。
   * CryoPayloadのVisual inspection.
   * φ800フランジは今日は開けておく。明日閉める。

  * IOO: *Kokeyama
   * 1WをMCに入れる。

  * 真空引き判断
   * チェックリスト最終確認。
   * 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。
   * おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。
   * Cryostatのタッチがないかを確認。
   * φ800フランジを閉める。

 
 * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.

 * Weekly
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
   * 1/19: Pump down.

  * Week of 1/22
   * 1/24,25 leak check.

  * Week of 1/29
   * 1/29 Cooling start
Line 78: Line 103:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * Type Bp: 正田(SRの作業の合間)

  * Laser hazard
   * 今日までIMMTより奥、明日の水曜からSRラインより奥に変更。

 * Weekly
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。

  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。


 * 問題点など
  * D-SUBケーブルがおかしくなったものが出た。 -> AEL
  * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS
  * 一部のカメラが表示されない(和泉、Stefan)。 -> 苔山
 * Issues
  * Network cableの整理
Line 114: Line 116:
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
Line 127: Line 133:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/16 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/18(Thur.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • Alignment: *Izumi
      • EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
      • ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
      • CryoPayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。

  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。
      • CryoPayloadのVisual inspection.

      • φ800フランジは今日は開けておく。明日閉める。
    • IOO: *Kokeyama
      • 1WをMCに入れる。
    • 真空引き判断
      • チェックリスト最終確認。
      • 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。
      • おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。
      • Cryostatのタッチがないかを確認。
      • φ800フランジを閉める。
  • Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.
  • Weekly
    • Week of 1/15
      • 1/15~ baffle PD installation
      • 1/16~ IOO works.
      • 1/17: Vacuum check meeting
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues
    • Network cableの整理

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1