Line 11: | Line 11: |
2017/11/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171114.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) * Beam leading to REFP port * *Izumi |
Line 19: | Line 25: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。 |
|
Line 60: | Line 54: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 63: | Line 57: |
2017/11/28(Tue.) | 2017/1/23(Tue.) |
Line 65: | Line 59: |
* Daily * 作業 * Type Bp: * インナーフレームの足が浮いているのでシムを入れて、傾きを補正して締め直したす。水平になっているはず。 * PRMを今日リリースする予定。 * アラインメント * PSLQPDでピッチ方向にずれ、MCTのQPDにヨー方向にずれがあった。IMMT1、2のアラインメントを取り直して、PR真空曹のフランジのセンターには当たった。 * メインビームのアラインメントは明日の水曜以降に続ける。 * WS * 昨日夕方から一部実際の作業が始まっている。 * 物の準備はだいたい完了。一部足りないものを持ち込むなどの作業がある。 |
* Remote participants by educe: None * Report of work (*:responsible person) * IOO: 苔山 * 精密空調が入って、温度が安定した。 * Vacuum * Oplevがヒートリンクで遮られていた。 * Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。 * 再度戻り光も確認した。 * 真空引きの準備がほぼ完了。 * BS:神津、Enzo * リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。 |
Line 78: | Line 75: |
* 作業人員(*:責任者) * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業) * Type Bp: 正田(SRの作業の合間) |
* Work plan (*:responsible person) * Vacuum * 昨日午後から延期になって、本日朝真空引き予定 * ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川 * コントロールルーム: 和泉、奥富 * Check listによる最終確認 |
Line 82: | Line 82: |
* Laser hazard * 今日までIMMTより奥、明日の水曜からSRラインより奥に変更。 |
* Laser hazard: 今日は午前はPSLのみ。午後からIMMT。 |
Line 86: | Line 85: |
* 11/27の週 * Commissioning Work Shop(11/27-12/1) * PRMの締め直しと、リリース。 * メインビームの再アラインメント。 |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
Line 91: | Line 89: |
* 12/4の週 * Type Aダンピングテスト。 * 12/11の週 * ETMYからの戻り光確認。 * 12/18EYC閉止。 |
* Week of 1/29 * 1/29,30 leak check. * Week of 2/5 * 2/5 Cooling start. |
Line 98: | Line 96: |
* 問題点など * D-SUBケーブルがおかしくなったものが出た。 -> AEL * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS * 一部のカメラが表示されない(和泉、Stefan)。 -> 苔山 |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 114: | Line 110: |
||10||2017/11/21||[[KAGRA/Commissioning/Weekly/20171121/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171121.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || | ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || |
Line 120: | Line 121: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 127: | Line 128: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/23(Tue.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- IOO: 苔山
- 精密空調が入って、温度が安定した。
- Vacuum
- Oplevがヒートリンクで遮られていた。
- Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。
- 再度戻り光も確認した。
- 真空引きの準備がほぼ完了。
BS:神津、Enzo
- リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。
- IOO: 苔山
- Work plan (*:responsible person)
- Vacuum
- 昨日午後から延期になって、本日朝真空引き予定
- ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川
- コントロールルーム: 和泉、奥富
- Check listによる最終確認
- 昨日午後から延期になって、本日朝真空引き予定
- Vacuum
- Laser hazard: 今日は午前はPSLのみ。午後からIMMT。
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)