Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person
 * Re alignment
  * 1/11 *Izumi
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 19: Line 29:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
Line 60: Line 58:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 61:
2017/11/29(Wed.) 2017/1/11(Thrs.)
Line 65: Line 63:
 * Daily
  * 作業
   * WS
    * 機能に引き続き作業。色々進捗が報告されている。
    * MCの戻り光を干渉なしで直接見ても復調信号にオフセットが乗っているのでどうやらAMが載っているようである。WFSの出力がそれぞれのQuadrantでサインが違うなどいろいろおかしい。
    * 全てのFanを一旦切ってからノイズを測定し、その後戻したので、もし戻し忘れていることがないか気をつけてください。
    * PSL出射光でのビームが楕円になっている。今日一度きちんと見て見る。今日何か変更することはない。
   * Type Bp:
    * PRMのリリースが完了。IMまではそこそこアラインメントは戻っているはず。WDが飛んでいるようなのでBIOをつないでチェックが必要。
    * メインビームのアラインメント終了後3次元測定をする。
 * Remote participants by educe: None
Line 76: Line 65:
   * Type B:
    * BSのアラインメントを再度とる。ダンピング作業も続ける。
   * アラインメント
    * メインビームのアラインメントを今週再度とる。うまくけばPR系に光が行くはず。
    * COACH filterのアサインメントとクリーンエアーのを確認する必要がある。
 * Report of work (*:responsible person)
Line 82: Line 67:
 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * Oplev, Re-alignment
Line 83: Line 71:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * アラインメント: 和泉、正田、道村
   * Type Bp: 正田
   * Type B: Mark、 Enzo、平田、神津、Fabian
  * Check of PLC at Yend for connection to measurement tools: Aso
Line 89: Line 73:

  * Laser hazard
   * 今日からSRラインより奥に変更。
  * Marionet Oplev: Akutsu
 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F
Line 94: Line 79:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.
Line 99: Line 83:
  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.
Line 105: Line 87:
  * Week of 1/22
   * 1/24,25 leak check.
Line 106: Line 90:
 * 問題点など
  * D-SUBケーブルがおかしくなったものが出た。 -> AEL
  * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS
  * Week of 1/29
   * 1/29 Cooling start

 * Issues
Line 121: Line 106:
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 134: Line 123:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/10 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/11 *Izumi
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/11(Thrs.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • Oplev, Re-alignment
    • Check of PLC at Yend for connection to measurement tools: Aso
    • Marionet Oplev: Akutsu
  • Laser hazard area
    • Behind of BS and SR line and Yend 1F
  • Weekly
    • Week of 1/8
      • 1/11, 12: Re-alignment for IFO.
      • 1/13, 14: Damping for ETMY.
    • Week of 1/15
      • IOO works.
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members