Differences between revisions 177 and 232 (spanning 55 versions)
Revision 177 as of 2017-11-30 09:22:22
Size: 7206
Comment:
Revision 232 as of 2018-01-09 09:10:27
Size: 6737
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/1/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}}
Line 19: Line 19:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
Line 60: Line 48:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 51:
2017/11/30(Thur.) 2017/1/9(Tue.)
Line 65: Line 53:
 * Daily
  * 作業
   * WS
    * 午後4時くらいにペリスコープに加速度計をつけようとして鏡を触ってしまい、ミスアラインメントが起きてしまった。PSLだけでは戻らなかったのでMCを少し動かした。午後6時くらいにはMC透過光ももとのレベルに戻った。
    * 入射光にAMが載っているのは事実のようである。EOMでのジッターがAMの原因か?-40dBmレベル。メインパワーとの比率は未測定。
    * PSL出射光でのビームが楕円になっている件は何か原因を見つけたようである。その過程で、他の改良点もいくつか見つかっている。
 * Remote participants by educe: Izumi, Yokozawa, Miyoki
Line 72: Line 55:
   * アラインメント
    * 昨日でPR3までビームが当たっていることまで確認できた。今日うまくけばエンドで光が再び見えるはず。
 * Report of work (*:responsible person)
  * IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。
  * Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。
  * Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。
Line 75: Line 60:
   * Type B:
    * BSのダンピングがかなり改善された。Oplevはまだセンサー内に光が戻ってきていない。
 * Work plan (*:responsible person)

 * Cryo: Yendの外回りの配線チェック。
  * 光てこの話と、真空中のPDの検討をする必要がある。
Line 79: Line 66:
  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * アラインメント: 和泉、正田、榎本
   * Type B: Mark、 Enzo、平田、正田


  * Laser hazard
   * 今日からSRラインより奥に変更。
 * Laser hazard
  * センターはIMM奥がハザードエリア。
Line 89: Line 70:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。
  * Week of 1/8
   * vacuum meeting 12:30 on 1/10, at fan hut.
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.
Line 94: Line 75:
  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.
Line 100: Line 79:
 * Issues
Line 101: Line 81:
 * 問題点など
  * D-SUBケーブルがおかしくなったものが出た。 -> 結局その先のフリッパーケーブルが問題であることが判明。KAGRA標準のD-SUBケーブルは問題ない。
  * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS
  * COACH filterのアサインメントとクリーンエアーのを確認する必要がある。->昨日は2台余っていたので、やりくりできそう。
Line 116: Line 92:
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 129: Line 108:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/5 updated KAGRA/Commissioning/Commissioning_schedule_20180109.png


Working people assignment

* 責任者



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/9(Tue.)

  • Remote participants by educe: Izumi, Yokozawa, Miyoki
  • Report of work (*:responsible person)
    • IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。
    • Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。
    • Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。
  • Work plan (*:responsible person)
  • Cryo: Yendの外回りの配線チェック。
    • 光てこの話と、真空中のPDの検討をする必要がある。
  • Laser hazard
    • センターはIMM奥がハザードエリア。
  • Weekly
    • Week of 1/8
      • vacuum meeting 12:30 on 1/10, at fan hut.
      • Re-alignment for IFO on 1/11, 12.
      • Damping for ETMY on 1/13, 14.
    • Week of 1/15
      • IOO works.
      • Pump down, leak check in the later of this week.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members