2017/11/28 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) * Beam leading to REFP port * *Izumi |
Line 19: | Line 25: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。 |
|
Line 60: | Line 54: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 63: | Line 57: |
2017/11/30(Thur.) | 2017/1/23(Tue.) |
Line 65: | Line 59: |
* Daily * 作業 * WS * 午後4時くらいにペリスコープに加速度計をつけようとして鏡を触ってしまい、ミスアラインメントが起きてしまった。PSLだけでは戻らなかったので、10uradくらいのオーダーでMCを少し動かした。午後6時くらいにはMC透過光ももとのレベルに戻った。 * 入射光にAMが載っているのは事実のようである。EOMでのジッターがAMの原因か?-40dBmレベル。メインパワーとの比率は未測定。 * PSL出射光でのビームが楕円になっている件: 何か原因を見つけたようである。その過程で、他にも改善図べき点もいくつか見つかっているので、リスト化する。 |
* Remote participants by educe: None |
Line 72: | Line 61: |
* アラインメント * 昨日でPR3までビームが当たっていることを確認できた。今日うまくけばエンドで光が再び見えるはず。 |
* Report of work (*:responsible person) * IOO: 苔山 * 精密空調が入って、温度が安定した。 |
Line 75: | Line 65: |
* Type B: * BSのダンピングがかなり改善された。Oplevはまだセンサー内に光が戻ってきていない。 |
* Vacuum * Oplevがヒートリンクで遮られていた。 * Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。 * 再度戻り光も確認した。 * 真空引きの準備がほぼ完了。 * BS:神津、Enzo * リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。 |
Line 79: | Line 75: |
* 作業人員(*:責任者) * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業) * アラインメント: 和泉、正田、榎本 * Type B: Mark、 Enzo、平田、正田 |
* Work plan (*:responsible person) * Vacuum * 昨日午後から延期になって、本日朝真空引き予定 * ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川 * コントロールルーム: 和泉、奥富 * Check listによる最終確認 * Laser hazard: 今日は午前はPSLのみ。午後からIMMT。 * Weekly * Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. * Week of 1/29 * 1/29,30 leak check. * Week of 2/5 * 2/5 Cooling start. |
Line 85: | Line 96: |
* Laser hazard * 今日からSRラインより奥に変更。 * Weekly * 11/27の週 * Commissioning Work Shop(11/27-12/1) * PRMの締め直しと、リリース。 * メインビームの再アラインメント。 * 12/4の週 * Type Aダンピングテスト。 * 12/11の週 * ETMYからの戻り光確認。 * 12/18EYC閉止。 * 問題点など * D-SUBケーブルがおかしくなったものが出た件 -> 結局その先のフリッパーケーブルが問題であることが判明。KAGRA標準のD-SUBケーブルは問題ない。 * COACH filterのアサインメントとクリーンエアーのを確認する必要がある。->昨日は2台余っていたので、やりくりできそう。 |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 115: | Line 110: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || |
|
Line 121: | Line 121: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 128: | Line 128: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/23(Tue.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- IOO: 苔山
- 精密空調が入って、温度が安定した。
- Vacuum
- Oplevがヒートリンクで遮られていた。
- Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。
- 再度戻り光も確認した。
- 真空引きの準備がほぼ完了。
BS:神津、Enzo
- リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。
- IOO: 苔山
- Work plan (*:responsible person)
- Vacuum
- 昨日午後から延期になって、本日朝真空引き予定
- ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川
- コントロールルーム: 和泉、奥富
- Check listによる最終確認
- 昨日午後から延期になって、本日朝真空引き予定
- Vacuum
- Laser hazard: 今日は午前はPSLのみ。午後からIMMT。
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)