Differences between revisions 179 and 244 (spanning 65 versions)
Revision 179 as of 2017-12-01 09:16:32
Size: 6670
Comment:
Revision 244 as of 2018-01-12 09:24:04
Size: 8383
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 19: Line 28:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
Line 60: Line 57:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 63: Line 60:
2017/12/1(Fri.) 2017/1/12(Fri.)
Line 65: Line 62:
 * Daily
  * 作業
   * WS
    * 午後に片付けをする。
   * アラインメント
    * 昨日はあまり進展なし。PR3まで。今日うまくけばエンドで光が再び見えるはず。
    * 来週月火に真空作業があるため時間調整が必要。
 * Remote participants by educe: None
Line 73: Line 64:
   * Type B:
    * Oplevに光が入った。もう少し解析に時間がかかる。大まかにはアラインメントはEYには向いている。
 * Affect of short power failure
  * VIS
   * EX のポラリティーが反転していた。瞬停と関係あるかは不明。
Line 76: Line 68:
   * Type A:
    * Y-endのケーブリングをしている。荷重テストと、YawのアラインメントをBFのピコモーターでする。ダンピングの進展具合は宮本君と確認。
  * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
   * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.

  * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.

 * Report of work (*:responsible person)
  * Alignment: *Izumi
   * X-armまでリカバーした。
   * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
    * GASは真空槽を開けずに直せる範囲を超えている模様。
    * PR3で100uradのオーダーでずれていた。
    * Oplevの範囲をすでに超えてしまっている。
Line 80: Line 82:
  * 作業人員(*:責任者)
   * WS: 麻生、*苔山、宮川 + 20名程度
   * アラインメント: 和泉、横澤、正田
   * Type B: Mark、 Enzo、平田、正田
   * Type A: 高橋、宮本
  * PLC at Yend: Aso
   * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。

  * Marionet Oplev: Akutsu
   * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
Line 87: Line 89:
  * Laser hazard
   * 今日からSRラインより奥に変更。
 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。

  * Marionet Oplev: Akutsu
   * QPDの信号を確認する予定。

 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F
Line 91: Line 101:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。
   * BSのダンピング
   * Type Aの接続
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.
Line 98: Line 105:
  * 12/4の週
   * Type Aダンピングテスト。
   * メインビームの再アラインメント。
   * 月、火にIYCでの真空作業がある。
  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.
Line 103: Line 109:
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * Week of 1/22
   * 1/24,25 leak check.
Line 107: Line 112:
  * Week of 1/29
   * 1/29 Cooling start
Line 108: Line 115:
 * 問題点など
   * 来週月、火に真空作業があり、ビームを止めて欲しいという要請が来ている。
 * Issues
   * EX のポラリティーが反転していた。回路の問題か?
   * 真空曹を開けてPR2とPR3を直すかどうか。
Line 121: Line 129:
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 134: Line 146:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/10 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/12(Fri.)

  • Remote participants by educe: None
  • Affect of short power failure
    • VIS
      • EX のポラリティーが反転していた。瞬停と関係あるかは不明。
    • IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
      • One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.
    • DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.
  • Report of work (*:responsible person)
    • Alignment: *Izumi
      • X-armまでリカバーした。
      • 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
        • GASは真空槽を開けずに直せる範囲を超えている模様。
        • PR3で100uradのオーダーでずれていた。
        • Oplevの範囲をすでに超えてしまっている。
    • PLC at Yend: Aso
      • 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。
    • Marionet Oplev: Akutsu
      • Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
    • Marionet Oplev: Akutsu
      • QPDの信号を確認する予定。
  • Laser hazard area
    • Behind of BS and SR line and Yend 1F
  • Weekly
    • Week of 1/8
      • 1/11, 12: Re-alignment for IFO.
      • 1/13, 14: Damping for ETMY.
    • Week of 1/15
      • IOO works.
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues
    • EX のポラリティーが反転していた。回路の問題か?
    • 真空曹を開けてPR2とPR3を直すかどうか。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)