Line 11: | Line 11: |
2017/11/28 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}} |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Re alignment * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 19: | Line 28: |
* PR系測定、PR2,PR3タンク蓋閉め * 11/16 木村、沢田、新井、*正田(蓋閉め) * 11/17 新井、*正田 * Watchdog測定, PRM release * 11/20 * * 11/21 * * 11/22 * * 11/23 * * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。 |
|
Line 60: | Line 57: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 63: | Line 60: |
2017/12/1(Fri.) | 2017/1/12(Fri.) |
Line 65: | Line 62: |
* Daily * 作業 * WS * 午後に片付けをする。 * アラインメント * 昨日はあまり進展なし。PR3まで。今日うまくけばエンドで光が再び見えるはず。 * 来週月火に真空作業があるため時間調整が必要。 |
* Remote participants by educe: None |
Line 73: | Line 64: |
* Type B: * Oplevに光が入った。もう少し解析に時間がかかる。大まかにはアラインメントはEYには向いている。 |
* Affect of short power failure * VIS * EX のポラリティーが反転していた。瞬停と関係あるかは不明。 |
Line 76: | Line 68: |
* Type A: * Y-endのケーブリングをしている。荷重テストと、YawのアラインメントをBFのピコモーターでする。ダンピングの進展具合は宮本君と確認。 |
* IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC. * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now. * Report of work (*:responsible person) * Alignment: *Izumi * X-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。 * GASは真空槽を開けずに直せる範囲を超えている模様。 * PR3で100uradのオーダーでずれていた。 * Oplevの範囲をすでに超えてしまっている。 |
Line 80: | Line 82: |
* 作業人員(*:責任者) * WS: 麻生、*苔山、宮川 + 20名程度 * アラインメント: 和泉、横澤、正田 * Type B: Mark、 Enzo、平田、正田 * Type A: 高橋、宮本 |
* PLC at Yend: Aso * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。 * Marionet Oplev: Akutsu * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。 |
Line 87: | Line 89: |
* Laser hazard * 今日からSRラインより奥に変更。 |
* Work plan (*:responsible person) * Alignment: *Izumi * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。 * Marionet Oplev: Akutsu * QPDの信号を確認する予定。 * Laser hazard area * Behind of BS and SR line and Yend 1F |
Line 91: | Line 101: |
* 11/27の週 * Commissioning Work Shop(11/27-12/1) * PRMの締め直しと、リリース。 * メインビームの再アラインメント。 * BSのダンピング * Type Aの接続 |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. |
Line 98: | Line 105: |
* 12/4の週 * Type Aダンピングテスト。 * メインビームの再アラインメント。 * 月、火にIYCでの真空作業がある。 |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
Line 103: | Line 109: |
* 12/11の週 * ETMYからの戻り光確認。 * 12/18EYC閉止。 |
* Week of 1/22 * 1/24,25 leak check. |
Line 107: | Line 112: |
* Week of 1/29 * 1/29 Cooling start |
|
Line 108: | Line 115: |
* 問題点など * 来週月、火に真空作業があり、ビームを止めて欲しいという要請が来ている。 |
* Issues * EX のポラリティーが反転していた。回路の問題か? * 真空曹を開けてPR2とPR3を直すかどうか。 |
Line 121: | Line 129: |
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || |
|
Line 134: | Line 146: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/10 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/12(Fri.)
- Remote participants by educe: None
- Affect of short power failure
- VIS
- EX のポラリティーが反転していた。瞬停と関係あるかは不明。
- IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
- One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.
- DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.
- VIS
- Report of work (*:responsible person)
- Alignment: *Izumi
- X-armまでリカバーした。
- 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
- GASは真空槽を開けずに直せる範囲を超えている模様。
- PR3で100uradのオーダーでずれていた。
- Oplevの範囲をすでに超えてしまっている。
- PLC at Yend: Aso
- 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。
- Marionet Oplev: Akutsu
- Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
- Alignment: *Izumi
- Work plan (*:responsible person)
- Alignment: *Izumi
- 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
- Marionet Oplev: Akutsu
- QPDの信号を確認する予定。
- Alignment: *Izumi
- Laser hazard area
- Behind of BS and SR line and Yend 1F
- Weekly
- Week of 1/8
- 1/11, 12: Re-alignment for IFO.
- 1/13, 14: Damping for ETMY.
- Week of 1/15
- IOO works.
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/8
- Issues
- EX のポラリティーが反転していた。回路の問題か?
- 真空曹を開けてPR2とPR3を直すかどうか。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)