Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person

 * Pump down
  * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)

 * Beam leading to REFP port
  * *Izumi
Line 19: Line 25:

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
 * ETMYアラインメント
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
 

Line 59: Line 54:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 62: Line 57:
2017/12/4(Mon.) 2017/1/23(Tue.)
Line 64: Line 59:
 * Daily
  * 作業 (*:責任者)
   * アラインメント: *和泉、大石、麻生
    * PR3のOSEMが当たってしまったために止まっている。今日明日で、今週中にエンドで光が再び見えるはず。
    * 来週月火に真空作業があるため時間調整が必要。IXCとIYCに挿フランジ、IYAのベローズを外す作業がある。今日はXのアラインメントでYは塞ぐ。
 * Remote participants by educe: Aso
Line 70: Line 61:
   * Type B: *Mark、平田
    * 新しいマトリックスを試す。ダンピングが改善される予定。
 * Report of work (*:responsible person)
  * None
Line 73: Line 64:
   * Type A: *宮本、高橋さん他
    * YエンドのTypeAとCryペイロードが繋がって、ケーブル接続などのインストールは終わった。今日DGS側との導通確認。
 * Work plan (*:responsible person)
  * Vacuum
   * 本日午後真空引き予定
    * ETMY立会い: 木村、鈴木、都丸、横澤、高橋(センター)、阿久津(センター)、宮川
    * コントロールルーム: 和泉、奥富
   * φ800フランジ締め
   * dial gaugeセット
   * Oplev確認
   * Tcam確認
   * Check listによる最終確認

 * IOO: 苔山
  * 午後にTilt sensorやPMCなどの作業あり。

  * Alignment: *Izumi
   * BS modelのテコ入れ: Izumi

 * Laser hazard: 今日は午前はPSL、午後からIMM、夕方から夜間にかけて全域。

 * Weekly
  * Week of 1/22
   * 1/23: Pump down.
   * 1/24: Turbo pump on.

  * Week of 1/29
   * 1/29,30 leak check.

  * Week of 2/5
   * 2/5 Cooling start.
Line 77: Line 95:
  * Laser hazard
   * 今日からSRラインより奥に変更。

 * Weekly
  * 12/4の週
   * Type Aダンピングテスト。
   * メインビームの再アラインメント。
   * 月、火にIYC、IXCでの真空作業がある。
   * 12/6,7: PR-BS相対位置測

  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。


 * 問題点など
   * PR-BS相対位置測定後、EXでの再位置測定が必要か?
 * Issues
  * Network cableの整理
Line 106: Line 108:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 119: Line 126:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/18 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Pump down
    • 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/23(Tue.)

  • Remote participants by educe: Aso
  • Report of work (*:responsible person)
    • None
  • Work plan (*:responsible person)
    • Vacuum
      • 本日午後真空引き予定
        • ETMY立会い: 木村、鈴木、都丸、横澤、高橋(センター)、阿久津(センター)、宮川
        • コントロールルーム: 和泉、奥富
      • φ800フランジ締め
      • dial gaugeセット
      • Oplev確認
      • Tcam確認
      • Check listによる最終確認
  • IOO: 苔山
    • 午後にTilt sensorやPMCなどの作業あり。
    • Alignment: *Izumi
      • BS modelのテコ入れ: Izumi
  • Laser hazard: 今日は午前はPSL、午後からIMM、夕方から夜間にかけて全域。
  • Weekly
    • Week of 1/22
      • 1/23: Pump down.
      • 1/24: Turbo pump on.
    • Week of 1/29
      • 1/29,30 leak check.
    • Week of 2/5
      • 2/5 Cooling start.
  • Issues
    • Network cableの整理

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)