Revision 185 as of 2017-12-07 09:39:17
Size: 7098
Comment:
Revision 269 as of 2018-01-25 09:07:27
Size: 7765
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/1/23 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person

 * Pump down
  * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)

 * Beam leading to REFP port
  * *Izumi
Line 19: Line 25:

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
 * ETMYアラインメント
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
 

Line 62: Line 57:
2017/12/7(Thur.) 2017/1/25(Thur.)
Line 64: Line 59:
 * Daily
  * 作業 (*:責任者)
   * 位置測定: *内山、寺田(V-11, 2831)
    * 昨日は準備。鏡の中心を測った。今日はビームの位置を比較確認。
 * Remote participants by educe: Miyoki, Akutsu
Line 69: Line 61:
   * アラインメント: 和泉(2829)
    * レーザー不調のため、アラインメントはそれほど進展がなかった。
    * レーザーはFSSがロックしなかった。AOMのドライバーが不調だったが、結局電源のバナナピンの接触不良が原因であることが判明。MCも復帰した。
    * ピコモーターのジョイスティックをつなげるところを間違えて、SMT1のピッチを動かしてしまった。そのためでFIを通っていない時間が存在する。FI後のQPDで確認しながら復帰。
    * 現在ETMXまでは光がいっている。
 * Report of work (*:responsible person)

  * Vacuum
   * 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。
   * ETMYを真空に引きはじめた。
   * 真空度がMEDM上で見えないので、ビデオカメラを設置した。

  * Alignment
   * Yaw方向に数100uradのオーダーで動いている。
   
  * AEL: k1iy0への電源ケーブルを張った。
Line 76: Line 74:
   * Type B: *Mark、平田、Fabian
    * 新しいマトリックスがうまくいって、キャリブレーションがとれた。そのためダンピングも改良できそう。
 * Work plan (*:responsible person)
  * Vacuum
   * Turbo pumpを入れる予定。
Line 79: Line 78:
   * Type A: *高橋(2637)、奥富
    * EYCのペイロードがBS方向に1cmずれていることが一昨日の時点で判明。ヒートリンクが引っ剝いている可能性がある。150gGの力でこれくらいのずれになる見込み。
    * トップは2mm程度のずれで、こちらは問題なさそう。
  * AEL: awai, tamori, hayakawa, nakada, yamamoto
Line 83: Line 80:
   * Cry: 宮本
    * actuatorのテストなどする予定。できれば伝達関数測定までしたい。

   * AEL: MC WFSで問題のあったI&Q demodulatorの3chテスト結果は、特に問題ないというものだった。よって坑内で何がダメだったのかは不明。

  * Laser hazard
   * SRラインより奥。
 * Laser hazard: Upstream of IMMT line
Line 92: Line 83:
  * 12/4の週
   * Type Aダンピングテスト。
   * メインビームの再アラインメント。
   * 月、火にIYC、IXCでの真空作業がある。
   * 12/6,7: PR-BS相対位置測
  * Week of 1/22
   * 1/24: Pump down.
   * 1/25: Turbo pump on.
Line 98: Line 87:
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
  * Week of 1/29
   * 1/29,30 leak check.

  * Week of 2/5
   * 2/5 Cooling start.
Line 103: Line 94:
 * 問題点など
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
 * Issues
  * Network cableの整理
  * ピコモーターの反応がなくなる。
Line 116: Line 108:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 122: Line 119:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 129: Line 126:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/23 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Pump down
    • 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/25(Thur.)

  • Remote participants by educe: Miyoki, Akutsu
  • Report of work (*:responsible person)
    • Vacuum
      • 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。
      • ETMYを真空に引きはじめた。
      • 真空度がMEDM上で見えないので、ビデオカメラを設置した。
    • Alignment
      • Yaw方向に数100uradのオーダーで動いている。
    • AEL: k1iy0への電源ケーブルを張った。
  • Work plan (*:responsible person)
    • Vacuum
      • Turbo pumpを入れる予定。
    • AEL: awai, tamori, hayakawa, nakada, yamamoto
  • Laser hazard: Upstream of IMMT line
  • Weekly
    • Week of 1/22
      • 1/24: Pump down.
      • 1/25: Turbo pump on.
    • Week of 1/29
      • 1/29,30 leak check.
    • Week of 2/5
      • 2/5 Cooling start.
  • Issues
    • Network cableの整理
    • ピコモーターの反応がなくなる。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1