Line 11: | Line 11: |
2017/12/11 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/11 * 12/12 和泉 * 12/13 和泉 * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/11 * 12/12 * 12/13 * 12/14 * 12/15 |
* Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 34: | Line 22: |
* BS PDセット * 12/11 * 12/12 横澤 * 12/13 横澤 * 12/14 * 12/15 |
* Beam leading to REFP port * *Izumi |
Line 73: | Line 57: |
2017/12/12(Tue.) | 2017/1/26(Fri.) |
Line 75: | Line 59: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: |
Line 78: | Line 61: |
* アラインメント: *和泉、苔山、野替 * 今日午後から、Xエンドのビームの確認、その後EYAに通す予定。PR2,3のOplevのダンピングをしたい。 * 現在PR3は固定してあるが、Phase1の間は固定したままで残すことを考えている。 * ワイヤーのテンションをきちんと張って落ち着かせる方法をVIRGOの人から聞いたので、とりあえずSRで試してみる予定。 |
* Report of work (*:responsible person) |
Line 83: | Line 63: |
* Type A: *高橋、奥富、宮本 * Oplevのキャリブレーションについてklogに報告があった。どれだけ進んでいるのか要確認。 * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。アルミホイルで塞ぐ方法もあるので、基本的に開ける方向で進める。 |
* Vacuum * ターボポンプを入れた。 |
Line 87: | Line 66: |
* PD設置: 横澤 * 明日PDをYendからBSに持ってくることになりそう。BSテーブルでのマウント方法を検討する必要がある。 |
* Alignment * Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。 * AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada * k1iy0への電源ケーブルの仕上げ。 * IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。 |
Line 90: | Line 73: |
* Type B: *Mark、Enzo, 正田 * 光学テーブルのアクチュエーターが一部働いていないところがあるのが見つかった。ハイパワーコイルドライバーでテストする。 |
* Work plan (*:responsible person) * 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。 * Alignment: Oplevのセンタリング。 |
Line 94: | Line 78: |
* Laser hazard * SRラインより奥。 |
* Laser hazard: Upstream of IMMT line |
Line 99: | Line 81: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
|
Line 100: | Line 85: |
* 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. * Week of 2/5 * 2/5 Cooling start. |
Line 107: | Line 93: |
* 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * BSテーブルにPDを置けるかどうか。 * Eendの遮蔽板をいつ開けるか。 * 真空引きの最終確認。 |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 124: | Line 107: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 131: | Line 118: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 138: | Line 125: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/26(Fri.)
- Remote participants by eZuce:
- Report of work (*:responsible person)
- Vacuum
- ターボポンプを入れた。
- Alignment
- Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。
- AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada
- k1iy0への電源ケーブルの仕上げ。
- IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。
- Vacuum
- Work plan (*:responsible person)
- 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。
- Alignment: Oplevのセンタリング。
- Laser hazard: Upstream of IMMT line
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- 1/30 Opening ETMY gate valve.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)