2017/12/11 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}}
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
 * Re alignment
  * 1/12 *Izumi
Line 20: Line 21:
 * ETMYアラインメント
  * 12/11
  * 12/12 和泉
  * 12/13 和泉
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
Line 34: Line 25:
 * BS PDセット
  * 12/11
  * 12/12 横澤
  * 12/13 横澤
  * 12/14
  * 12/15
 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 73: Line 60:
2017/12/12(Tue.) 2017/1/18(Thur.)
Line 75: Line 62:
 * Daily
  * 報告と作業 (*:責任者)
 * Remote participants by educe: None
Line 78: Line 64:
   * アラインメント: *和泉、苔山、野替
    * 今日午後から、Xエンドのビームの確認、その後EYAに通す予定。
     * その際、PR2,3のOplevのダンピングをしたい。
     * 現在PR3は固定してあるが、Phase1の間は固定したままで残すことを考えている。
     * ワイヤーのテンションをきちんと張って落ち着かせる方法をVIRGOの人から聞いたので、とりあえずSRで試してみる予定。
 * Report of work (*:responsible person)
  * Vacuum
   * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
Line 84: Line 68:
   * Type A: *高橋、奥富、宮本
    * Oplevのキャリブレーションについてklogに報告があった。どれだけ進んでいるのか要確認。
    * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。アルミホイルで塞ぐ方法もあるので、基本的に開ける方向で進める。
  * IOO: *Kokeyama
   * 1WがMCに入った。
Line 88: Line 71:
   * PD設置: 横澤
    * 明日PDをYendからBSに持ってくることになりそう。BSテーブルでのマウント方法を検討する必要がある。
  * Alignment: *Izumi
   * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
   * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
   * ETMYからの戻り光をリサージュで一晩降ったが見つかっていない。スリットを再び入れる予定。
Line 91: Line 76:
   * Type B: *Mark、Enzo, 正田
    * 光学テーブルのアクチュエーターが一部働いていないところがあるのが見つかった。ハイパワーコイルドライバーでテストする。ドライバーが足りなくなって来ているので、SRでまだ使っていないものを持ってくる。
 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
   * 11時頃まで作業のためにレーザーハザードは全域。11時から通常のIMMより手前に戻す。
Line 95: Line 82:
  * 真空引きの最終判断は月曜日にする。
   * チェックリスト最終確認。
   * φ800フランジを閉める。
Line 96: Line 86:
  * Laser hazard
   * SRラインより奥。
   * Laser hazard: All area until 11AM, then changed to ipstream of IMM line. Hayakawa will change the border by 11AM.
Line 100: Line 90:
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
Line 101: Line 95:
  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。
  * Week of 1/22
   * 1/23: Pump down.
   * 1/29,30 leak check.

  * Week of 1/29
   * 1/29 Cooling start
Line 108: Line 103:
 * 問題点など
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * BSテーブルにPDを置けるかどうか。
  * Eendの遮蔽板をいつ開けるか。
  * 真空引きの最終確認。
 * Issues
  * Network cableの整理
  * Cryostatがタッチしている可能性あり。
  * ビームアラインメントの最終確認が時間的にぎりぎり。
Line 125: Line 118:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
Line 139: Line 136:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/18 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/18(Thur.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • Vacuum
      • Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
    • IOO: *Kokeyama
      • 1WがMCに入った。
    • Alignment: *Izumi
      • ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
      • Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
      • ETMYからの戻り光をリサージュで一晩降ったが見つかっていない。スリットを再び入れる予定。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
      • 11時頃まで作業のためにレーザーハザードは全域。11時から通常のIMMより手前に戻す。
    • 真空引きの最終判断は月曜日にする。
      • チェックリスト最終確認。
      • φ800フランジを閉める。
  • Laser hazard: All area until 11AM, then changed to ipstream of IMM line. Hayakawa will change the border by 11AM.
  • Weekly
    • Week of 1/15
      • 1/15~ baffle PD installation
      • 1/16~ IOO works.
      • 1/17: Vacuum check meeting
    • Week of 1/22
      • 1/23: Pump down.
      • 1/29,30 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues
    • Network cableの整理
    • Cryostatがタッチしている可能性あり。
    • ビームアラインメントの最終確認が時間的にぎりぎり。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1