Differences between revisions 201 and 265 (spanning 64 versions)
Revision 201 as of 2017-12-13 09:18:10
Size: 7485
Comment:
Revision 265 as of 2018-01-23 09:12:58
Size: 7856
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}}
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
Line 20: Line 19:
 * ETMYアラインメント
  * 12/13 和泉
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/13
  * 12/14
  * 12/15
 * Pump down
  * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 30: Line 22:
 * BS PDセット
  * 12/13 横澤
  * 12/14
  * 12/15
 * Beam leading to REFP port
  * *Izumi
Line 67: Line 57:
2017/12/13(Wed.) 2017/1/23(Tue.)
Line 69: Line 59:
 * Daily
  * 報告と作業 (*:責任者)
 * Remote participants by educe: Aso
Line 72: Line 61:
   * アラインメント: *和泉
    * YendのPDに光を届けた。BSを特にいじることなく、すぐに光が通った。PR2のダンピングを調整する必要があった。
    * BSは依然10uradくらいのオーダーで揺れている。
 * Report of work (*:responsible person)
  * None
Line 76: Line 64:
   * Type B: *Mark、Enzo, 正田, 和泉
    * IP yaw, IM, TMのpitchのダンピングを入れた。
    * Yawの動きがまだ大きい。これは全体の回転のようである。上のマグネティックダンパーで減衰されるはずがうまく効いていない。
    * サスペンション全体が4mm程度下に下がっているかもしれない。
    * 蓋を開けなければならないので、今日やることを考える。

   * Type A: *高橋、宮本、牛場
    * Yawが回転したが、力がある閾値を超えるとガクッと回るような感じである。ベアリングが渋い可能性が高い。
    * 回るのも数分のオーダーで、微調整がかなり厳しそう。回転の方向は正しいことは確認した。
    * BFのダンピングを強くするともう少し素直に反応する可能性がある。
    * 今日は上部のダンピング制御を入れて操作して様子を見てみる。DC制御か?

   * PD設置:
 * Work plan (*:responsible person)
  * Vacuum
   * 本日午後真空引き予定
    * ETMY立会い: 木村、鈴木、都丸、横澤、高橋(センター)、阿久津(センター)、宮川
    * コントロールルーム: 和泉、奥富
   * φ800フランジ締め
   * dial gaugeセット
   * Oplev確認
   * Tcam確認
   * Check listによる最終確認
Line 91: Line 76:
  * Alignment: *Izumi
   * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
   * 11時頃からレーザーハザードを全域に変更してアラインメント作業。

  * BS modelのテコ入れ: Izumi

 * Laser hazard: 今日は午前はPSL、午後からIMM、夕方から夜間にかけて全域。

 * Weekly
  * Week of 1/22
   * 1/23: Pump down.
   * 1/24: Turbo pump on.

  * Week of 1/29
   * 1/29,30 leak check.

  * Week of 2/5
   * 2/5 Cooling start.
Line 93: Line 96:
  * Laser hazard
   * SRラインより奥。
   * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。

 * Weekly

  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。


 * 問題点など
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * BSテーブルにPDを置けるかどうか。
  * Eendの遮蔽板をいつ開けるか。
  * 真空引きの最終確認。
 * Issues
  * Network cableの整理
Line 123: Line 109:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
Line 137: Line 127:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/18 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Pump down
    • 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/23(Tue.)

  • Remote participants by educe: Aso
  • Report of work (*:responsible person)
    • None
  • Work plan (*:responsible person)
    • Vacuum
      • 本日午後真空引き予定
        • ETMY立会い: 木村、鈴木、都丸、横澤、高橋(センター)、阿久津(センター)、宮川
        • コントロールルーム: 和泉、奥富
      • φ800フランジ締め
      • dial gaugeセット
      • Oplev確認
      • Tcam確認
      • Check listによる最終確認
    • Alignment: *Izumi
      • EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
      • 11時頃からレーザーハザードを全域に変更してアラインメント作業。
    • BS modelのテコ入れ: Izumi
  • Laser hazard: 今日は午前はPSL、午後からIMM、夕方から夜間にかけて全域。
  • Weekly
    • Week of 1/22
      • 1/23: Pump down.
      • 1/24: Turbo pump on.
    • Week of 1/29
      • 1/29,30 leak check.
    • Week of 2/5
      • 2/5 Cooling start.
  • Issues
    • Network cableの整理

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members