Line 11: Line 11:
2017/12/12 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}}
2017/1/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}}
Line 18: Line 18:
     * ETMYアラインメント
  * 12/13 和泉
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/13
  * 12/14
  * 12/15

 * BS PDセット
  * 12/13 横澤
  * 12/14
  * 12/15
Line 67: Line 51:
2017/12/13(Wed.) 2017/1/9(Tue.)
Line 69: Line 53:
 * Daily
  * 本日12時半よりファン小屋で真空関連の打ち合わせ。
   * 出席予定者:
    * 木村、宮川、牛場、高橋、都丸、和泉
    * (eZuce) 阿久津、井上
 * Remote participants by educe: Izumi, Yokozawa, Miyoki
Line 75: Line 55:
  * 報告と作業 (*:責任者)  * Report of work (*:responsible person)
  * IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。
  * Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。
  * Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。
Line 77: Line 60:
   * アラインメント: *和泉
    * YendのPDに光を届けた。BSを特にいじることなく、すぐに光が通った。PR2のダンピングを調整する必要があった。
    * BSは依然10uradくらいのオーダーで揺れている。
 * Work plan (*:responsible person)
Line 81: Line 62:
   * Type B: *Mark、Enzo, 正田, 和泉
    * IP yaw, IM, TMのpitchのダンピングを入れた。
    * Yawの動きがまだ大きい。これは全体の回転のようである。上のマグネティックダンパーで減衰されるはずがうまく効いていない。
    * サスペンション全体が4mm程度下に下がっているかもしれない。
    * 蓋を開けなければならないので、今日やることを考える。

   * Type A: *牛場、宮本
    * Yawが回転したが、力がある閾値を超えるとガクッと回るような感じである。ベアリングが渋い可能性が高い。
    * 回るのも数分のオーダーで、微調整がかなり厳しそう。回転の方向は正しいことは確認した。
    * BFのダンピングを強くするともう少し素直に反応する可能性がある。
    * 今日は上部のダンピング制御を入れて操作して様子を見てみる。DC制御か?

   * PD設置:
 * Cryo: Yendの外回りの配線チェック。
  * 光てこの話と、真空中のPDの検討をする必要がある。
Line 96: Line 66:


  * Laser hazard
   * SRラインより奥。
   * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
 * Laser hazard
  * センターはIMM奥がハザードエリア。
Line 103: Line 70:
  * Week of 1/8
   * vacuum meeting 12:30 on 1/10, at fan hut.
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.
Line 104: Line 75:
  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。
  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.
Line 110: Line 79:
 * Issues
Line 111: Line 81:
 * 問題点など
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * BSテーブルにPDを置けるかどうか。
  * Eendの遮蔽板をいつ開けるか。
  * 真空引きの最終確認。
Line 128: Line 92:
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
Line 142: Line 108:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/5 updated KAGRA/Commissioning/Commissioning_schedule_20180109.png


Working people assignment

* 責任者



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/9(Tue.)

  • Remote participants by educe: Izumi, Yokozawa, Miyoki
  • Report of work (*:responsible person)
    • IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。
    • Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。
    • Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。
  • Work plan (*:responsible person)
  • Cryo: Yendの外回りの配線チェック。
    • 光てこの話と、真空中のPDの検討をする必要がある。
  • Laser hazard
    • センターはIMM奥がハザードエリア。
  • Weekly
    • Week of 1/8
      • vacuum meeting 12:30 on 1/10, at fan hut.
      • Re-alignment for IFO on 1/11, 12.
      • Damping for ETMY on 1/13, 14.
    • Week of 1/15
      • IOO works.
      • Pump down, leak check in the later of this week.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings