Line 11: Line 11:
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
 * Re alignment
  * 1/11 *Izumi
  * 1/12 *Izumi
Line 20: Line 22:
 * ETMYアラインメント
  * 12/14 和泉、長野、川﨑
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/14
  * 12/15
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
Line 28: Line 26:
 * BS PDセット
  * 12/14 横澤
  * 12/15

 * 遮蔽板取り外し
  * 木村
 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 67: Line 61:
2017/12/14(Thu.) 2017/1/11(Thrs.)
Line 69: Line 63:
 * Daily
  * 報告と作業 (*:責任者)
 * Remote participants by educe: None
Line 72: Line 65:
   * 遮蔽板取り外し: *木村、その他
    * 朝から取り外し作業開始。終了次第宮川まで連絡。
 * Report of work (*:responsible person)
Line 75: Line 67:
   * アラインメント: *和泉、長野、川崎、三代木
    * ダンピング周りを見直している。PR3は0.2uradくらにまでなっている。
    * 遮蔽板の取り外しが終わり次第アラインメント開始。
     * ETMYのType A部分にモーターのスタックなどあるが、アラインメントには支障がなさそうなので、ETMYからの戻り光を確認するアラインメント作業は今日、明日で決行する。
 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * Oplev, Re-alignment
Line 80: Line 71:
   * Type B: *Mark、Enzo, 正田, 和泉
    * 昨日言っていたキーストーンが4mm低いというのはLVDTのキャリブレーションの間違い。実際にはキーストンの位置を1.5mm上げた。
     * それでもダンピングはまだ効いていないようである。
    * IMのコントロールをアップデートした。多少改善したが、いまやっと10uradくらいの揺れになったくらい。
  * Check of PLC at Yend for connection to measurement tools: Aso
Line 85: Line 73:
   * Type A: *牛場、宮本
    * Fishing rodの稼働実験をした。結果は残念ながら動かなかった。
     * さらに作業中に、別件として新たにモーターが端まで行ってしまってstuckしてしまった。
     * unstuckできるのが最速で月曜日。月曜のフタ締めの準備中にやるか?
     * この問題は垂直方向のことなので、アラインメント作業には直接は影響なさそう。


   * PD設置:
    * 和泉君の指示で移動のタイミングを横澤君に知らせる。
     * 時期としては今日の午後か、明日の午前くらい。



  * Laser hazard
   * SRラインより奥。
   * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。
  * Marionet Oplev: Akutsu
 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F
Line 103: Line 79:
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.
Line 104: Line 83:
  * 12/11の週
   * メインビームの再アラインメント。
   * ETMYからの戻り光確認。
   * 12/13 昼休みに真空引きの前のミーティング。
   * 12/18 EYC閉止。
  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.
Line 110: Line 87:
  * 12/18の週
   * EYC閉止
  * Week of 1/22
   * 1/24,25 leak check.
Line 113: Line 90:
  * Week of 1/29
   * 1/29 Cooling start
Line 114: Line 93:
 * Issues
Line 115: Line 95:
 * 問題点など
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
  * PR系のスリップが頻発している。特にPR3。
  * WSのアカウントを個別にしてほしい。(和泉、その他) -> LDAPを入れなければならず、結構大変(山本、宮川)
Line 130: Line 106:
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
Line 144: Line 123:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/10 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/11 *Izumi
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/11(Thrs.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • Oplev, Re-alignment
    • Check of PLC at Yend for connection to measurement tools: Aso
    • Marionet Oplev: Akutsu
  • Laser hazard area
    • Behind of BS and SR line and Yend 1F
  • Weekly
    • Week of 1/8
      • 1/11, 12: Re-alignment for IFO.
      • 1/13, 14: Damping for ETMY.
    • Week of 1/15
      • IOO works.
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)