7152
Comment:
|
8395
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person * Re alignment * 1/12 *Izumi |
Line 20: | Line 21: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto |
Line 26: | Line 25: |
* BS PDセット * 12/15 横澤 |
* Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 62: | Line 60: |
2017/12/15(Fri.) | 2017/1/12(Fri.) |
Line 64: | Line 62: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by educe: None |
Line 67: | Line 64: |
* アラインメント: *和泉、長野、川崎、榎本 * BSのアルミ箔を外し、EYのPDに光をあてる。 * IMMT2のピコモーターがスタックしているようなのでそれを直す。 * EYのPDを回収して、スリットを使いEYのアラインメントをする。 * Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。 * BSで光が見えたらゴール。 |
* Affect of short power failure * VIS * EX のポラリティーが反転していた。瞬停と関係あるかは不明。 |
Line 74: | Line 68: |
* Type B(BS): *正田、和泉、長野 * TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。 |
* IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC. |
Line 77: | Line 71: |
* Type A(ETMY): *牛場、宮本 * 揺れはOplevでみて数uradになっている。 * アラインメントはなんとか出るところまでは持っていけた。 |
* DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now. |
Line 81: | Line 73: |
* PD設置: *横澤 * 和泉君の指示で移動のタイミングを横澤君に知らせる。 |
* Report of work (*:responsible person) * Alignment: *Izumi * X-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。 * GASは真空槽を開けずに直せる範囲を超えている模様。 * PR3で100uradのオーダーでずれていた。 * Oplevの範囲をすでに超えてしまっている。 |
Line 84: | Line 81: |
* BSカメラ設置: *苔山、長野 * 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。 |
|
Line 87: | Line 82: |
* Laser hazard * センターは変わらずSR奥。 * 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。 |
* PLC at Yend: Aso * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。 * Marionet Oplev: Akutsu * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。 * Work plan (*:responsible person) * Alignment: *Izumi * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。 * Marionet Oplev: Akutsu * QPDの信号を確認する予定。 * Laser hazard area * Behind of BS and SR line and Yend 1F |
Line 92: | Line 101: |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. |
|
Line 93: | Line 105: |
* 12/11の週 * ETMYからの戻り光確認。 |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
Line 96: | Line 109: |
* 12/18の週 * EYC閉止 |
* Week of 1/22 * 1/24,25 leak check. |
Line 99: | Line 112: |
* Week of 1/29 * 1/29 Cooling start |
|
Line 100: | Line 115: |
* 問題点など |
* Issues * EX のポラリティーが反転していた。回路の問題か? * 真空曹を開けてPR2とPR3を直すかどうか。 |
Line 113: | Line 129: |
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 127: | Line 146: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/10 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/12(Fri.)
- Remote participants by educe: None
- Affect of short power failure
- VIS
- EX のポラリティーが反転していた。瞬停と関係あるかは不明。
- IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
- One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.
- DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.
- VIS
- Report of work (*:responsible person)
- Alignment: *Izumi
- X-armまでリカバーした。
- 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
- GASは真空槽を開けずに直せる範囲を超えている模様。
- PR3で100uradのオーダーでずれていた。
- Oplevの範囲をすでに超えてしまっている。
- PLC at Yend: Aso
- 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。
- Marionet Oplev: Akutsu
- Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
- Alignment: *Izumi
- Work plan (*:responsible person)
- Alignment: *Izumi
- 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
- Marionet Oplev: Akutsu
- QPDの信号を確認する予定。
- Alignment: *Izumi
- Laser hazard area
- Behind of BS and SR line and Yend 1F
- Weekly
- Week of 1/8
- 1/11, 12: Re-alignment for IFO.
- 1/13, 14: Damping for ETMY.
- Week of 1/15
- IOO works.
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/8
- Issues
- EX のポラリティーが反転していた。回路の問題か?
- 真空曹を開けてPR2とPR3を直すかどうか。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools