Size: 7041
Comment:
|
Size: 7998
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
* Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 26: | Line 22: |
* BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Izumi |
Line 62: | Line 57: |
2017/12/18(Mon.) | 2017/1/26(Fri.) |
Line 64: | Line 59: |
* Daily * 作業報告および作業予定 (*:責任者) * アラインメント: *和泉、長野、榎本、川崎 * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。 * BFのピコモーターが離散的に動く。5mrad程度のステップ。 * BFを固定した方がアラインメントはやりやすいのでは?(都丸) * アラインメントは今日はなし。 |
* Remote participants by eZuce: |
Line 72: | Line 61: |
* Type A(ETMY): *牛場、宮本 * バネが動きを吸収している可能性があるので、バネを変える。 * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった? * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。 * 今日蓋閉めの準備のためにその作業をするので、 * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。 * 火曜日の夕方に方向性を判断。 |
* Report of work (*:responsible person) |
Line 80: | Line 63: |
* PD設置: *横澤、和泉 * BSチェンバー内、AS側に設置完了。 * EYAにいってViewポートを取り付ける。 |
* Vacuum * ターボポンプを入れた。 |
Line 84: | Line 66: |
* BSカメラ設置: *苔山、川崎 * BS付近に設置したが、レンズ交換が必要。 |
* Alignment * Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。 * AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada * k1iy0への電源ケーブルの仕上げ。 * IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。 * Work plan (*:responsible person) * 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。 * Alignment: Oplevのセンタリング。 |
Line 88: | Line 78: |
* Laser hazard * センターはSR奥がハザードエリア。エンドはハザードエリアなし。 |
* Laser hazard: Upstream of IMMT line |
Line 92: | Line 81: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
|
Line 93: | Line 85: |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. * Week of 2/5 * 2/5 Cooling start. |
Line 98: | Line 93: |
* 問題点など * 回路電源のモニターがあるといい。 |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 113: | Line 107: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 120: | Line 118: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 127: | Line 125: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/26(Fri.)
- Remote participants by eZuce:
- Report of work (*:responsible person)
- Vacuum
- ターボポンプを入れた。
- Alignment
- Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。
- AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada
- k1iy0への電源ケーブルの仕上げ。
- IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。
- Vacuum
- Work plan (*:responsible person)
- 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。
- Alignment: Oplevのセンタリング。
- Laser hazard: Upstream of IMMT line
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- 1/30 Opening ETMY gate valve.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools