Size: 7241
Comment:
|
Size: 7765
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
* Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 26: | Line 22: |
* BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Izumi |
Line 62: | Line 57: |
2017/12/18(Mon.) | 2017/1/25(Thur.) |
Line 64: | Line 59: |
* 作業報告 (*:責任者) * アラインメント: *和泉、長野、榎本、川崎 * BSのアラインメントはうまくいった。COACHを切って角度揺れで0.1urad程度。 * BFのピコモーターが離散的に動く。5mrad程度のステップ。 |
* Remote participants by educe: Miyoki, Akutsu |
Line 69: | Line 61: |
* Type A(ETMY): *牛場、宮本、都丸、和泉 * ベアリングを押しているバネが動きを吸収している可能性がある。 |
* Report of work (*:responsible person) |
Line 72: | Line 63: |
* PD設置: *横澤、和泉、井上 * BSチェンバー内、AS側に設置完了。 |
* Vacuum * 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。 * ETMYを真空に引きはじめた。 * 真空度がMEDM上で見えないので、ビデオカメラを設置した。 |
Line 75: | Line 68: |
* BSカメラ設置: *苔山、川崎 * BS付近に設置したが、レンズ交換が必要。 * 作業予定 (*:責任者) * アラインメント: *和泉、都丸 * BFを固定した方がアラインメントはやりやすいのでは?(都丸) * Type A(ETMY): *高橋、牛場、都丸、和泉 * バネを変える。 * Fishing rodのスタックを戻す。LVDTの信号を見ながら動かす。電源がおかしかった? * Fishing rodのリリースと、バネの交換のためにCryoPayloadを一旦固定して、リリースする必要がある。 * 今日、明日くらいが蓋閉めの準備のためにその作業をするので、その間に解決することを目標にする。 * 粗調はIPでやる必要があるが、可動範囲は+/-5mrad程度はあるはず。人員(奥富)を確保する必要がある。 * 火曜日の夕方に方向性を判断。 * PD設置: *横澤、井上 * EYAにいってViewポートを取り付ける。 |
* Alignment * Yaw方向に数100uradのオーダーで動いている。 * AEL: k1iy0への電源ケーブルを張った。 |
Line 94: | Line 74: |
* Laser hazard * センターはSR奥がハザードエリア。エンドはハザードエリアなし。 |
* Work plan (*:responsible person) * Vacuum * Turbo pumpを入れる予定。 * AEL: awai, tamori, hayakawa, nakada, yamamoto * Laser hazard: Upstream of IMMT line |
Line 98: | Line 83: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
|
Line 99: | Line 87: |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 |
* Week of 1/29 * 1/29,30 leak check. * Week of 2/5 * 2/5 Cooling start. |
Line 104: | Line 94: |
* 問題点など * 回路電源のモニターがあるといい。 |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 118: | Line 108: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 125: | Line 119: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 132: | Line 126: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/25(Thur.)
- Remote participants by educe: Miyoki, Akutsu
- Report of work (*:responsible person)
- Vacuum
- 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。
- ETMYを真空に引きはじめた。
- 真空度がMEDM上で見えないので、ビデオカメラを設置した。
- Alignment
- Yaw方向に数100uradのオーダーで動いている。
- AEL: k1iy0への電源ケーブルを張った。
- Vacuum
- Work plan (*:responsible person)
- Vacuum
- Turbo pumpを入れる予定。
- AEL: awai, tamori, hayakawa, nakada, yamamoto
- Vacuum
- Laser hazard: Upstream of IMMT line
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools