Differences between revisions 216 and 243 (spanning 27 versions)
Revision 216 as of 2017-12-19 09:40:48
Size: 7677
Comment:
Revision 243 as of 2018-01-11 09:12:28
Size: 6987
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/14 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}}
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
 * Re alignment
  * 1/11 *Izumi
  * 1/12 *Izumi
Line 20: Line 22:
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
Line 26: Line 26:
 * BS PDセット
  * 12/15 横澤
 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 62: Line 61:
2017/12/19(Tue.) 2017/1/11(Thrs.)
Line 64: Line 63:
 * 作業報告 (*:責任者)
  * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本
   * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。
   * Fishing rodのスタックも直した。
 * Remote participants by educe: None
Line 69: Line 65:
  * Vierport: *横澤、井上
   * EYAにViewport設置完了。
 * Report of work (*:responsible person)
Line 72: Line 67:
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * コイルドライバーがおかしい可能性がある。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
   * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。
 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * Oplev, Re-alignment
Line 78: Line 71:
 * 作業予定 (*:責任者)
  * アラインメント: *和泉
   * 今日の昼休み12時から1時の間にスリットを置く。
  * Check of PLC at Yend for connection to measurement tools: Aso
Line 82: Line 73:
  * Type A(ETMY): *高橋、牛場、都丸、和泉
   * Fishing rodが動くか確認。

  * IOO
   * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。
   * MCの調子が悪い。



 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 午後からYend 1Fがハザートエリアになる。
  * Marionet Oplev: Akutsu
 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F
Line 96: Line 79:
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.
Line 97: Line 83:
  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
   * ETMYのアラインメント
  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.
Line 102: Line 87:
  * Week of 1/22
   * 1/24,25 leak check.
Line 103: Line 90:
 * 問題点など
  * 回路電源のモニターがあるといい。
  * MCの調子が悪い。
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
  * Week of 1/29
   * 1/29 Cooling start

 * Issues
Line 121: Line 106:
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 136: Line 123:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/10 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/11 *Izumi
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/11(Thrs.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • Oplev, Re-alignment
    • Check of PLC at Yend for connection to measurement tools: Aso
    • Marionet Oplev: Akutsu
  • Laser hazard area
    • Behind of BS and SR line and Yend 1F
  • Weekly
    • Week of 1/8
      • 1/11, 12: Re-alignment for IFO.
      • 1/13, 14: Damping for ETMY.
    • Week of 1/15
      • IOO works.
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)