Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
* Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 26: | Line 22: |
* BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Izumi |
Line 62: | Line 57: |
2017/12/19(Tue.) | 2017/1/25(Thur.) |
Line 64: | Line 59: |
* 作業報告 (*:責任者) * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本 * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。 * Fishing rodのスタックも直した。 |
* Remote participants by educe: Miyoki, Akutsu |
Line 69: | Line 61: |
* Vierport: *横澤、井上 * EYAにViewport設置完了。 |
* Report of work (*:responsible person) |
Line 72: | Line 63: |
* IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * コイルドライバーがおかしい可能性がある。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。 |
* Vacuum * 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。 * ETMYを真空に引きはじめた。 * 真空度がMEDM上で見えないので、ビデオカメラを設置した。 |
Line 78: | Line 68: |
* 作業予定 (*:責任者) * アラインメント: *和泉 * 今日の昼休み12時から1時の間にスリットを置く。 * Type A(ETMY): *高橋、牛場、都丸、和泉 * Fishing rodが動くか確認。 * IOO * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。 * MCの調子が悪い。 |
* Alignment * Yaw方向に数100uradのオーダーで動いている。 * AEL: k1iy0への電源ケーブルを張った。 |
Line 90: | Line 74: |
* Work plan (*:responsible person) * Vacuum * Turbo pumpを入れる予定。 |
|
Line 91: | Line 78: |
* Laser hazard * センターはSR奥がハザードエリア。 * 午後からYend 1Fがハザートエリアになる。 |
* AEL: awai, tamori, hayakawa, nakada, yamamoto * Laser hazard: Upstream of IMMT line |
Line 96: | Line 83: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
|
Line 97: | Line 87: |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 * ETMYのアラインメント |
* Week of 1/29 * 1/29,30 leak check. * Week of 2/5 * 2/5 Cooling start. |
Line 103: | Line 94: |
* 問題点など * 回路電源のモニターがあるといい。 * MCの調子が悪い。 * IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 |
* Issues * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 121: | Line 108: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 129: | Line 119: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 136: | Line 126: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/25(Thur.)
- Remote participants by educe: Miyoki, Akutsu
- Report of work (*:responsible person)
- Vacuum
- 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。
- ETMYを真空に引きはじめた。
- 真空度がMEDM上で見えないので、ビデオカメラを設置した。
- Alignment
- Yaw方向に数100uradのオーダーで動いている。
- AEL: k1iy0への電源ケーブルを張った。
- Vacuum
- Work plan (*:responsible person)
- Vacuum
- Turbo pumpを入れる予定。
- AEL: awai, tamori, hayakawa, nakada, yamamoto
- Vacuum
- Laser hazard: Upstream of IMMT line
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)