Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/1/16 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者
  
 * *: responsible person
 * Re alignment
  * 1/12 *Izumi
Line 20: Line 21:
 * ETMYアラインメント
  * 12/15 和泉、長野、川﨑、榎本
 
 * GigEカメラセット
  * 12/15 苔山、川﨑
 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
Line 26: Line 25:
 * BS PDセット
  * 12/15 横澤
 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 62: Line 60:
2017/12/19(Tue.) 2017/1/16(Tue.)
Line 64: Line 62:
 * 作業報告 (*:責任者)
  * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本
   * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。
   * Fishing rodのスタックも直した。
 * Remote participants by educe: Inoue
Line 69: Line 64:
  * Vierport: *横澤、井上
   * EYAにViewport設置完了。
 * Report of work (*:responsible person)
  * Alignment: *Izumi
   * Baffle PDを入れるので、その回路を用意している。Oplev回路を改造してつかう。
Line 72: Line 68:
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * コイルドライバーがおかしい可能性がある。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
   * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。
  * BS: 新井
   * L2Pをフィルターを設計した。DCもそこそ、高周波もかなりいったが、すごく低い周波数はもう少し改良する必要がある。
Line 78: Line 71:
 * 作業予定 (*:責任者)
  * アラインメント: *和泉
   * 今日の昼休み12時から1時の間にスリットを置く。
 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * EYでものの準備など。
Line 82: Line 75:
  * Type A(ETMY): *高橋、牛場、都丸、和泉
   * Fishing rodが動くか確認。
   * Laser hazard: Upstream of IMM line.
Line 85: Line 78:
  * IOO
   * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。
   * MCの調子が悪い。
 * Weekly
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
   * 1/19: Pump down.

  * Week of 1/22
   * 1/24,25 leak check.

  * Week of 1/29
   * 1/29 Cooling start
Line 90: Line 92:

 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 午後からYend 1Fがハザートエリアになる。

 * Weekly

  * 12/18の週
   * EYC閉止
   * Type A引き続き調整。
   * ETMYのアラインメント


 * 問題点など
  * 回路電源のモニターがあるといい。
  * MCの調子が悪い。
  * IMMTが動かない件
   * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。
   * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。
 * Issues
Line 121: Line 104:
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 136: Line 121:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/16 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/16(Tue.)

  • Remote participants by educe: Inoue
  • Report of work (*:responsible person)
    • Alignment: *Izumi
      • Baffle PDを入れるので、その回路を用意している。Oplev回路を改造してつかう。
    • BS: 新井
      • L2Pをフィルターを設計した。DCもそこそ、高周波もかなりいったが、すごく低い周波数はもう少し改良する必要がある。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • EYでものの準備など。
  • Laser hazard: Upstream of IMM line.
  • Weekly
    • Week of 1/15
      • 1/15~ baffle PD installation
      • 1/16~ IOO works.
      • 1/17: Vacuum check meeting
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools