Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/1/18 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person * Re alignment * 1/12 *Izumi |
Line 20: | Line 21: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto |
Line 26: | Line 25: |
* BS PDセット * 12/15 横澤 |
* Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 62: | Line 60: |
2017/12/19(Tue.) | 2017/1/19(Thur.) |
Line 64: | Line 62: |
* 作業報告 (*:責任者) * Type A(ETMY): *牛場、石崎、佐藤、都丸、宮本 * BFのYawがきちんと動いた。CryopayloadがEQ stopの付近が当たっていたことが原因。ログにはバネを交換したと書いてあるが、実際にはバネは交換していない。ローカルにラフなアラインメントをとった。 * Fishing rodのスタックも直した。 |
* Remote participants by educe: None |
Line 69: | Line 64: |
* Vierport: *横澤、井上 * EYAにViewport設置完了。 |
* Report of work (*:responsible person) * Vacuum * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY. |
Line 72: | Line 68: |
* IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * コイルドライバーがおかしい可能性がある。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 * アラインメントはピコモーターでするので、上記トラブルはアラインメントには関係ない。 |
* IOO: *Kokeyama * 1WがMCに入った。 |
Line 78: | Line 71: |
* 作業予定 (*:責任者) * アラインメント: *和泉 * 今日の昼休み12時から1時の間にスリットを置く。 |
* Alignment: *Izumi * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。 * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。 * ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。 |
Line 82: | Line 76: |
* Type A(ETMY): *高橋、牛場、都丸、和泉 * Fishing rodが動くか確認。 * IOO * ISSの作業がある。昼の12時から1時にレーサーが必要なのでMCロックまで含めてレーザーを出す。 * MCの調子が悪い。 |
* Work plan (*:responsible person) * Alignment: *Izumi * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。 * 11時頃からレーザーハザードを全域に変更してアラインメント作業。 |
Line 90: | Line 82: |
* 真空引きの最終判断は月曜日にする。 * チェックリスト最終確認。 * φ800フランジを閉める。 |
|
Line 91: | Line 86: |
* Laser hazard * センターはSR奥がハザードエリア。 * 午後からYend 1Fがハザートエリアになる。 |
* Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM. |
Line 96: | Line 90: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting |
|
Line 97: | Line 95: |
* 12/18の週 * EYC閉止 * Type A引き続き調整。 * ETMYのアラインメント |
* Week of 1/22 * 1/23: Pump down. * 1/24: Turbo pump on. * Week of 1/29 * 1/29,30 leak check. * 1/31? Cooling start. |
Line 103: | Line 104: |
* 問題点など * 回路電源のモニターがあるといい。 * MCの調子が悪い。 * IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 |
* Issues * Network cableの整理 |
Line 121: | Line 117: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 136: | Line 135: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/18 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/19(Thur.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Vacuum
- Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
- IOO: *Kokeyama
- 1WがMCに入った。
- Alignment: *Izumi
- ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
- Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
- ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。
- Vacuum
- Work plan (*:responsible person)
- Alignment: *Izumi
- EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
- 11時頃からレーザーハザードを全域に変更してアラインメント作業。
- 真空引きの最終判断は月曜日にする。
- チェックリスト最終確認。
- φ800フランジを閉める。
- Alignment: *Izumi
- Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM.
- Weekly
- Week of 1/15
- 1/15~ baffle PD installation
- 1/16~ IOO works.
- 1/17: Vacuum check meeting
- Week of 1/22
- 1/23: Pump down.
- 1/24: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- 1/31? Cooling start.
- Week of 1/15
- Issues
- Network cableの整理
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)