7590
Comment:
|
7911
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person * Re alignment * 1/12 *Izumi |
Line 20: | Line 21: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto |
Line 26: | Line 25: |
* BS PDセット * 12/15 横澤 |
* Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 62: | Line 60: |
2017/12/20(Wed.) | 2017/1/15(Mon.) |
Line 64: | Line 62: |
* 作業報告 (*:責任者) * Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋 * BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく戻った。 * スリットを使うことで、BS側に戻すのも相当楽だった。 * ETMYのPayloadのトーションに200uradくらいの揺れが残っている。ダンピングが必要。Pitchも数十uradくらい揺れている。Pitchはおそらく上からのエアー。 * Yendで14000カウントでていたがBSで6000カウントになった。コンシステント。 |
* Remote participants by educe: None |
Line 71: | Line 64: |
* IMMTが動かない件 * IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度おきている。 * DACカードの順序が入れ替わっているようである。->DGS |
* Report of work (*:responsible person) * Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo * ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。 * BSのLを押してPが出ないようにするフィルターを実装している。DCはうまくいったが高周波がまだ十分でない。 * 先週の時点で干渉計ビームはX-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。PR系を直すのは来週以降に延期。 |
Line 75: | Line 71: |
* IOO: 苔山、古畑、坂本、北澤 * アラインメントがほぼ完了。 |
* 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。 |
Line 78: | Line 73: |
* 作業予定 (*:責任者) * Alignment of ETMY: *和泉、高橋、牛場、都丸、 * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。 |
* Work plan (*:responsible person) * Alignment: *Izumi * Baffle PDを入れるので、その回路を用意する。 |
Line 82: | Line 77: |
* IOO | * PLC at Yend: Aso * MEDMを作成している。 * Laser hazard: to be changed to IMM line in the morning. * Weekly * Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. * Week of 1/29 * 1/29 Cooling start |
Line 85: | Line 96: |
* Laser hazard * センターはSR奥がハザードエリア。 * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。 * Weekly * Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 * Week of 12/25 * 停電の可能性あり。 * 問題点など * 回路電源のモニターがあるといい。 * MCの調子が悪い。 * IMMTが動かない件 * EPICS IOCの調子がおかしい。AWGが動かない。DAQのチャンネル名を直したい。 * アクチュエーターの効率のデザイン値が小さすぎる。Yawは100uradくらいレンジがあるが、pitchのレンジが小さすぎる。 |
* Issues |
Line 119: | Line 108: |
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 134: | Line 125: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/10 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/15(Mon.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo
- ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。
- BSのLを押してPが出ないようにするフィルターを実装している。DCはうまくいったが高周波がまだ十分でない。
- 先週の時点で干渉計ビームはX-armまでリカバーした。
- 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。PR系を直すのは来週以降に延期。
- 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。
- Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo
- Work plan (*:responsible person)
- Alignment: *Izumi
- Baffle PDを入れるので、その回路を用意する。
- PLC at Yend: Aso
- MEDMを作成している。
- Alignment: *Izumi
- Laser hazard: to be changed to IMM line in the morning.
- Weekly
- Week of 1/15
- 1/15~ baffle PD installation
- 1/16~ IOO works.
- 1/17: Vacuum check meeting
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/15
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools