Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
* Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 26: | Line 22: |
* BS PDセット * 12/15 横澤 |
* Beam leading to REFP port * *Izumi |
Line 62: | Line 57: |
2017/12/21(Thu.) | 2017/1/26(Fri.) |
Line 64: | Line 59: |
* Report of work (*:責任者) * Alignment of ETMY: *Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。 |
* Remote participants by eZuce: |
Line 68: | Line 61: |
* BS: Oplevの位置の初期化をしたい。 | * Report of work (*:responsible person) |
Line 70: | Line 63: |
* Work plan (*:責任者) | * Vacuum * ターボポンプを入れた。 * Alignment * Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。 * AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada * k1iy0への電源ケーブルの仕上げ。 * IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。 * Work plan (*:responsible person) * 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。 * Alignment: Oplevのセンタリング。 |
Line 73: | Line 78: |
* Laser hazard * センターはSR奥がハザードエリア。 * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。 |
* Laser hazard: Upstream of IMMT line |
Line 78: | Line 81: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
|
Line 79: | Line 85: |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. |
Line 84: | Line 89: |
* Week of 12/25 * Planed power outage in the afternoon on 12/15. |
* Week of 2/5 * 2/5 Cooling start. |
Line 89: | Line 94: |
* k1imcでDACの入れ替えが起こっている | * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 101: | Line 107: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 109: | Line 118: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 116: | Line 125: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/26(Fri.)
- Remote participants by eZuce:
- Report of work (*:responsible person)
- Vacuum
- ターボポンプを入れた。
- Alignment
- Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。
- AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada
- k1iy0への電源ケーブルの仕上げ。
- IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。
- Vacuum
- Work plan (*:responsible person)
- 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。
- Alignment: Oplevのセンタリング。
- Laser hazard: Upstream of IMMT line
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- 1/30 Opening ETMY gate valve.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)