Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 17: Line 17:
* 責任者
  * Green setting on PR2:
   * 12/26 *Akutsu, Yokogawa + 1 or 2
   * 12/27 *Yokogawa + 1 or 2
 * *: responsible person
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 54: Line 60:
2017/12/21(Thu.) 2017/1/18(Thur.)

 * Remote participants by educe: None
Line 57: Line 65:
  * Alignment of ETMY: *Izumi, Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa
   * BS: ETMYに光を当てた状態で、Oplevの位置の初期化をして0点に合わせた。
   * Type Aのリリースはできなかった。
  * Alignment: *Izumi
   * EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
   * ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
   * CryopayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。
Line 62: Line 71:
  * No main work today.   * Alignment: *Izumi
   * 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。
   * CryopayloadのVisual inspection.
   * φ800フランジは今日は開けておく。明日閉める。
Line 64: Line 76:
  * IOO: *Kokeyama
   * 1WをMCに入れる。
Line 65: Line 79:
 * Laser hazard
   * センターはSR奥がハザードエリア。
  * 真空引き判断
   * チェックリスト最終確認。
   * 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。
   * おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。
   * Cryostatのタッチがないかを確認。
   * φ800フランジを閉める。

 
 * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.
Line 69: Line 90:
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
   * 1/19: Pump down.
Line 70: Line 96:
  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。
  * Week of 1/22
   * 1/24,25 leak check.
Line 75: Line 99:
 * Week of 12/25
  * Planed power outage in the afternoon on 12/15.
  * Week of 1/29
   * 1/29 Cooling start
Line 80: Line 104:
  * k1imcでDACの入れ替えが起こっている   * Network cableの整理
  * Cryostatがタッチしている可能性あり。
  * ビームアラインメントの最終確認が時間的にぎりぎり。
Line 92: Line 118:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 107: Line 136:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/18 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/18(Thur.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • Alignment: *Izumi
      • EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
      • ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
      • CryopayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。
      • CryopayloadのVisual inspection.
      • φ800フランジは今日は開けておく。明日閉める。
    • IOO: *Kokeyama
      • 1WをMCに入れる。
    • 真空引き判断
      • チェックリスト最終確認。
      • 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。
      • おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。
      • Cryostatのタッチがないかを確認。
      • φ800フランジを閉める。
  • Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.
  • Weekly
    • Week of 1/15
      • 1/15~ baffle PD installation
      • 1/16~ IOO works.
      • 1/17: Vacuum check meeting
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues
    • Network cableの整理
    • Cryostatがタッチしている可能性あり。
    • ビームアラインメントの最終確認が時間的にぎりぎり。

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1