Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 * Green setting on PR2: * 12/26 *Akutsu, Yokogawa + 1 or 2 * 12/27 *Yokogawa + 1 or 2 |
* *: responsible person * Pump down * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) * Beam leading to REFP port * *Izumi |
Line 54: | Line 57: |
2017/12/22(Fri.) | 2017/1/25(Thur.) * Remote participants by educe: Miyoki, Akutsu |
Line 57: | Line 62: |
* Alignment of ETMY: *Ushiba, Sato, Takahashi R, Miyamoto, Tomaru, Yokozawa * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。 |
* Vacuum * 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。 * ETMYを真空に引きはじめた。 * 真空度がMEDM上で見えないので、ビデオカメラを設置した。 * Alignment * Yaw方向に数100uradのオーダーで動いている。 * AEL: k1iy0への電源ケーブルを張った。 |
Line 61: | Line 75: |
* 停電のために真空層の蓋を閉める。(内山) | * Vacuum * Turbo pumpを入れる予定。 |
Line 63: | Line 78: |
* AEL: awai, tamori, hayakawa, nakada, yamamoto | |
Line 64: | Line 80: |
* Laser hazard * センターはSR奥がハザードエリア。 |
* Laser hazard: Upstream of IMMT line |
Line 68: | Line 83: |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
|
Line 69: | Line 87: |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 |
* Week of 1/29 * 1/29,30 leak check. |
Line 74: | Line 90: |
* Week of 12/25 * Planed power outage in the afternoon on 12/25. |
* Week of 2/5 * 2/5 Cooling start. |
Line 79: | Line 95: |
* k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい | * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 91: | Line 108: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 99: | Line 119: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 106: | Line 126: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/25(Thur.)
- Remote participants by educe: Miyoki, Akutsu
- Report of work (*:responsible person)
- Vacuum
- 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。
- ETMYを真空に引きはじめた。
- 真空度がMEDM上で見えないので、ビデオカメラを設置した。
- Alignment
- Yaw方向に数100uradのオーダーで動いている。
- AEL: k1iy0への電源ケーブルを張った。
- Vacuum
- Work plan (*:responsible person)
- Vacuum
- Turbo pumpを入れる予定。
- AEL: awai, tamori, hayakawa, nakada, yamamoto
- Vacuum
- Laser hazard: Upstream of IMMT line
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)