Comment:
|
6987
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 * Green setting on PR2: * 12/26 *Akutsu, Yokogawa + 1 or 2 * 12/27 *Yokogawa + 1 or 2 |
* *: responsible person * Re alignment * 1/11 *Izumi * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 54: | Line 61: |
2017/12/22(Fri.) | 2017/1/11(Thrs.) * Remote participants by educe: None |
Line 57: | Line 66: |
* Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。 |
|
Line 61: | Line 68: |
* 停電のために真空層の蓋を閉める。(内山) | * Alignment: *Izumi * Oplev, Re-alignment |
Line 63: | Line 71: |
* Check of PLC at Yend for connection to measurement tools: Aso | |
Line 64: | Line 73: |
* Laser hazard * センターはSR奥がハザードエリア。 |
* Marionet Oplev: Akutsu * Laser hazard area * Behind of BS and SR line and Yend 1F |
Line 68: | Line 79: |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. |
|
Line 69: | Line 83: |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
Line 74: | Line 87: |
* Week of 12/25 * Planed power outage in the afternoon on 12/25. |
* Week of 1/22 * 1/24,25 leak check. |
Line 77: | Line 90: |
* Week of 1/29 * 1/29 Cooling start |
|
Line 79: | Line 94: |
* k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい | |
Line 91: | Line 106: |
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 106: | Line 123: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/10 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/11 *Izumi
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/11(Thrs.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Work plan (*:responsible person)
- Alignment: *Izumi
- Oplev, Re-alignment
- Check of PLC at Yend for connection to measurement tools: Aso
- Marionet Oplev: Akutsu
- Alignment: *Izumi
- Laser hazard area
- Behind of BS and SR line and Yend 1F
- Weekly
- Week of 1/8
- 1/11, 12: Re-alignment for IFO.
- 1/13, 14: Damping for ETMY.
- Week of 1/15
- IOO works.
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/8
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools