Differences between revisions 223 and 247 (spanning 24 versions)
Revision 223 as of 2017-12-22 09:06:29
Size: 6335
Comment:
Revision 247 as of 2018-01-15 09:13:54
Size: 8208
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
Line 17: Line 17:
* 責任者
  * Green setting on PR2:
   * 12/26 *Akutsu, Yokogawa + 1 or 2
   * 12/27 *Yokogawa + 1 or 2
 * *: responsible person
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 54: Line 60:
2017/12/22(Fri.) 2017/1/15(Mon.)

 * Remote participants by educe: None
Line 57: Line 65:
  * Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa
   * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。
  * Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo
   * ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。
   * BSのLを押してPが出ないようにする。DCはうまくいったが高周波がまだ十分でない。
  * 干渉計ビームはX-armまでリカバーした。
   * 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。直すのは延期。

  * 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。


  * Marionet Oplev: Akutsu
   * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
Line 61: Line 79:
  * 停電のために真空層の蓋を閉める。(内山)   * Alignment: *Izumi
   * Buffule PDを入れるので、その回路を用意する。
Line 63: Line 82:
   * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
Line 64: Line 84:
 * Laser hazard
   * センターはSR奥がハザードエリア。
  * PLC at Yend: Aso
   * MEDMを作成している。
 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F
Line 68: Line 91:
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.
Line 69: Line 95:
  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。
  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.
Line 74: Line 99:
 * Week of 12/25
  * Planed power outage in the afternoon on 12/25.
  * Week of 1/22
   * 1/24,25 leak check.
Line 77: Line 102:
  * Week of 1/29
   * 1/29 Cooling start

 * Laser hazard: to be changed to IMM line in the morning.
Line 79: Line 108:
  * k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい
Line 91: Line 119:
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 106: Line 136:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/10 updated KAGRA/Commissioning/Commissioning_schedule_20180116.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/15(Mon.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • Alignment: *Izumi, Ushiba, Okutomi, Miyamoto, Arai, Miyo, Kozu, Miyakawa, Yamamoto, Akutsu, Tomaru, Miyo
      • ETMYのダンピングとBSのL2P。ETMYは100urad程度だったのが、10uradくらいになった。あと一桁欲しい。
      • BSのLを押してPが出ないようにする。DCはうまくいったが高周波がまだ十分でない。
    • 干渉計ビームはX-armまでリカバーした。
      • 中央エリア内の温度変化によりPR2とPR3のGASが数mmのオーダーで上に上がってピッチが変わったが、角度でいうと10uradくらいのオーダーでずれるだけなのでOK, ただビームスポットはcmのオーダーでずれる。直すのは延期。
    • 温度が一旦下がってから一度くらい上がった。問題なければ今のを保つ。
    • Marionet Oplev: Akutsu
      • Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • Buffule PDを入れるので、その回路を用意する。
      • 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
    • PLC at Yend: Aso
      • MEDMを作成している。
  • Laser hazard area
    • Behind of BS and SR line and Yend 1F
  • Weekly
    • Week of 1/8
      • 1/11, 12: Re-alignment for IFO.
      • 1/13, 14: Damping for ETMY.
    • Week of 1/15
      • IOO works.
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Laser hazard: to be changed to IMM line in the morning.
  • Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)