Differences between revisions 229 and 259 (spanning 30 versions)
Revision 229 as of 2018-01-05 10:25:55
Size: 6324
Comment:
Revision 259 as of 2018-01-18 15:54:04
Size: 8831
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 51: Line 60:
2017/1/5(Fri.) 2017/1/18(Thur.)
Line 55: Line 64:
 * 停電からの復帰関連
  * DGS: PR3も復帰した。DACが一枚不調だった。k1imcのDACを一枚抜いた。入れ替えは直っているはず。
  * IOO: MCまで復帰。回路も特に問題ない。
  * 真空: MC再起動。腕はまだ(来週)。
  * Tcam: 2秒間隔で見えるようになった。
 * Report of work (*:responsible person)
  * Alignment: *Izumi
   * EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
   * ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
   * CryopayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。

 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。
   * CryopayloadのVisual inspection.
   * φ800フランジは今日は開けておく。明日閉める。

  * IOO: *Kokeyama
   * 1WをMCに入れる。

  * 真空引き判断
   * チェックリスト最終確認。
   * 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。
   * おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。
   * Cryostatのタッチがないかを確認。
   * φ800フランジを閉める。

 
 * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.

 * Weekly
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
   * 1/19: Pump down.

  * Week of 1/22
   * 1/24,25 leak check.

  * Week of 1/29
   * 1/29 Cooling start
Line 62: Line 103:
 * Report of work (*:responsible person)
  * Type A: Remoteで測定していた模様。

 * Work plan (*:responsible person)


 * Laser hazard
  * センターはIMM奥がハザードエリア。

 * Weekly
  * Week of 1/5

  * Week of 1/8
   * meeting
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.

  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.
Line 84: Line 104:
  * Remoteでの接続が遅い。VPNかk1gateのDNSか?
  * Network cableの整理
  * Cryostatがタッチしている可能性あり。
  * ビームアラインメントの最終確認が時間的にぎりぎり。
Line 97: Line 118:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
Line 112: Line 136:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/18 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/18(Thur.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • Alignment: *Izumi
      • EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
      • ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
      • CryopayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。
      • CryopayloadのVisual inspection.
      • φ800フランジは今日は開けておく。明日閉める。
    • IOO: *Kokeyama
      • 1WをMCに入れる。
    • 真空引き判断
      • チェックリスト最終確認。
      • 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。
      • おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。
      • Cryostatのタッチがないかを確認。
      • φ800フランジを閉める。
  • Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.
  • Weekly
    • Week of 1/15
      • 1/15~ baffle PD installation
      • 1/16~ IOO works.
      • 1/17: Vacuum check meeting
      • 1/19: Pump down.
    • Week of 1/22
      • 1/24,25 leak check.
    • Week of 1/29
      • 1/29 Cooling start
  • Issues
    • Network cableの整理
    • Cryostatがタッチしている可能性あり。
    • ビームアラインメントの最終確認が時間的にぎりぎり。

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)