Line 11: | Line 11: |
2017/1/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}} |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 | * *: responsible person * Re alignment * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 51: | Line 60: |
2017/1/9(Tue.) | 2017/1/12(Fri.) |
Line 53: | Line 62: |
* Remote participants by educe: Izumi, Yokozawa, Miyoki | * Remote participants by educe: None * Affect of short power failure * VIS * EX のポラリティーが反転していた。瞬停と関係あるかは不明。 * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC. * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now. |
Line 56: | Line 74: |
* IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。 * Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。 * Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。 |
* Alignment: *Izumi * X-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。 * GASは真空槽を開けずに直せる範囲を超えている模様。 * PR3で100uradのオーダーでずれていた。 * Oplevの範囲をすでに超えてしまっている。 * PLC at Yend: Aso * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。 * Marionet Oplev: Akutsu * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。 |
Line 61: | Line 90: |
* Alignment: *Izumi * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。 |
|
Line 62: | Line 93: |
* Cryo: Yendの外回りの配線チェック。 * 光てこの話と、真空中のPDの検討をする必要がある。 |
* Marionet Oplev: Akutsu * QPDの信号を確認する予定。 |
Line 65: | Line 96: |
* Laser hazard * センターはIMM奥がハザードエリア。 |
* Laser hazard area * Behind of BS and SR line and Yend 1F |
Line 71: | Line 102: |
* vacuum meeting 12:30 on 1/10, at fan hut. * Re-alignment for IFO on 1/11, 12. * Damping for ETMY on 1/13, 14. |
* 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. |
Line 77: | Line 107: |
* Pump down, leak check in the later of this week. | * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. * Week of 1/29 * 1/29 Cooling start |
Line 80: | Line 116: |
* EX のポラリティーが反転していた。回路の問題か? * 真空曹を開けてPR2とPR3を直すかどうか。 |
|
Line 92: | Line 129: |
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || | |
Line 108: | Line 146: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/10 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/12(Fri.)
- Remote participants by educe: None
- Affect of short power failure
- VIS
- EX のポラリティーが反転していた。瞬停と関係あるかは不明。
- IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
- One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.
- DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.
- VIS
- Report of work (*:responsible person)
- Alignment: *Izumi
- X-armまでリカバーした。
- 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
- GASは真空槽を開けずに直せる範囲を超えている模様。
- PR3で100uradのオーダーでずれていた。
- Oplevの範囲をすでに超えてしまっている。
- PLC at Yend: Aso
- 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。
- Marionet Oplev: Akutsu
- Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
- Alignment: *Izumi
- Work plan (*:responsible person)
- Alignment: *Izumi
- 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
- Marionet Oplev: Akutsu
- QPDの信号を確認する予定。
- Alignment: *Izumi
- Laser hazard area
- Behind of BS and SR line and Yend 1F
- Weekly
- Week of 1/8
- 1/11, 12: Re-alignment for IFO.
- 1/13, 14: Damping for ETMY.
- Week of 1/15
- IOO works.
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/8
- Issues
- EX のポラリティーが反転していた。回路の問題か?
- 真空曹を開けてPR2とPR3を直すかどうか。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)