2017/1/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180109.png||width=1200}}
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto

 * Pump down
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Line 51: Line 60:
2017/1/9(Tue.) 2017/1/19(Thur.)
Line 53: Line 62:
 * Remote participants by educe: Izumi, Yokozawa, Miyoki  * Remote participants by educe: None
Line 56: Line 65:
  * IOO: 地震でMCのアラインメントがずれた。5uradから50uradのオーダー。
  * Type A: 年末年始はXendの伝達測定をしていた。Yendは特にリモートからは何をしていない。
  * Type B, Bp: 地震でのジャンプはあったが、十分補正できる範囲でたいした量ではなかった。他にBSとPR系のYawのドリフトが100uadのオーダーで大きくずれていたが、まだ直してはいない。
  * Vacuum
   * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.

  * IOO: *Kokeyama
   * 1WがMCに入った。

  * Alignment: *Izumi
   * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
   * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
   * ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。
Line 61: Line 77:

 * Cryo: Yendの外回りの配線チェック。
  * 光てこの話と、真空中のPDの検討をする必要がある。
  * Alignment: *Izumi
   * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
   * 11時頃からレーザーハザードを全域に変更してアラインメント作業。
Line 66: Line 82:
 * Laser hazard
  * センターはIMM奥がハザードエリア。
  * 真空引きの最終判断は月曜日にする。
   * チェックリスト最終確認。
   * φ800フランジを閉める。

 
 * Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM.
Line 70: Line 90:
  * Week of 1/8
   * vacuum meeting 12:30 on 1/10, at fan hut.
   * Re-alignment for IFO on 1/11, 12.
   * Damping for ETMY on 1/13, 14.
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
Line 75: Line 95:
  * Week of 1/15
   * IOO works.
   * Pump down, leak check in the later of this week.
  * Week of 1/22
   * 1/23: Pump down.
   * 1/24: Turbo pump on.

  * Week of 1/29
   * 1/29,30 leak check.
   * 1/31? Cooling start.
Line 80: Line 105:
  * Network cableの整理
Line 92: Line 117:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
Line 108: Line 135:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/18 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Re alignment
    • 1/12 *Izumi
  • Damping for ETMY
    • 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
    • 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
  • Pump down
    • 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/19(Thur.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • Vacuum
      • Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
    • IOO: *Kokeyama
      • 1WがMCに入った。
    • Alignment: *Izumi
      • ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
      • Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
      • ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
      • 11時頃からレーザーハザードを全域に変更してアラインメント作業。
    • 真空引きの最終判断は月曜日にする。
      • チェックリスト最終確認。
      • φ800フランジを閉める。
  • Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM.
  • Weekly
    • Week of 1/15
      • 1/15~ baffle PD installation
      • 1/16~ IOO works.
      • 1/17: Vacuum check meeting
    • Week of 1/22
      • 1/23: Pump down.
      • 1/24: Turbo pump on.
    • Week of 1/29
      • 1/29,30 leak check.
      • 1/31? Cooling start.
  • Issues
    • Network cableの整理

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)