Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/11 *Izumi * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto |
|
Line 27: | Line 20: |
* 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) | * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) * Beam leading to REFP port * *Izumi |
Line 61: | Line 57: |
2017/1/11(Thrs.) | 2017/1/25(Thur.) |
Line 63: | Line 59: |
* Remote participants by educe: None | * Remote participants by educe: Miyoki, Akutsu |
Line 67: | Line 63: |
* Vacuum * 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。 * ETMYを真空に引きはじめた。 * 真空度がMEDM上で見えないので、ビデオカメラを設置した。 * Alignment * Yaw方向に数100uradのオーダーで動いている。 * AEL: k1iy0への電源ケーブルを張った。 |
|
Line 68: | Line 75: |
* Alignment: *Izumi * Oplev, Re-alignment |
* Vacuum * Turbo pumpを入れる予定。 |
Line 71: | Line 78: |
* Check of PLC at Yend for connection to measurement tools. * Laser hazard area * Behind of BS and SR line and Yend 1F |
* AEL: awai, tamori, hayakawa, nakada, yamamoto * Laser hazard: Upstream of IMMT line |
Line 77: | Line 83: |
* Week of 1/8 * vacuum meeting 12:30 on 1/10, at fan hut. * Re-alignment for IFO on 1/11, 12. * Damping for ETMY on 1/13, 14. |
* Week of 1/22 * 1/24: Pump down. * 1/25: Turbo pump on. |
Line 82: | Line 87: |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
* Week of 1/29 * 1/29,30 leak check. |
Line 86: | Line 90: |
* Week of 1/22 * 1/24,25 leak check. |
* Week of 2/5 * 2/5 Cooling start. |
Line 90: | Line 95: |
* Network cableの整理 * ピコモーターの反応がなくなる。 |
|
Line 102: | Line 108: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || | |
Line 112: | Line 119: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 119: | Line 126: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Pump down
- 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/25(Thur.)
- Remote participants by educe: Miyoki, Akutsu
- Report of work (*:responsible person)
- Vacuum
- 朝の時点で昨日少しだけ引いた真空度は変わっていなかったため、簡易リークチェックはOK。
- ETMYを真空に引きはじめた。
- 真空度がMEDM上で見えないので、ビデオカメラを設置した。
- Alignment
- Yaw方向に数100uradのオーダーで動いている。
- AEL: k1iy0への電源ケーブルを張った。
- Vacuum
- Work plan (*:responsible person)
- Vacuum
- Turbo pumpを入れる予定。
- AEL: awai, tamori, hayakawa, nakada, yamamoto
- Vacuum
- Laser hazard: Upstream of IMMT line
- Weekly
- Week of 1/22
- 1/24: Pump down.
- 1/25: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/22
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)