Line 11: Line 11:
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/1/23 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Kozu, Yamamoto
Line 26: Line 20:
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)   * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)

 * Beam leading to REFP port
  * *Izumi
Line 60: Line 57:
2017/1/12(Fri.) 2017/1/23(Tue.)
Line 64: Line 61:
 * Affect of short power failure
  * VIS
   * EX のポラリティーが反転していた。瞬停と関係あるかは不明。
 * Report of work (*:responsible person)
  * IOO: 苔山
   * 精密空調が入って、温度が安定した。
Line 68: Line 65:
  * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
   * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.
  * Vacuum
   * Oplevがヒートリンクで遮られていた。
   * Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。
    * 再度戻り光も確認した。
   * 真空引きの準備がほぼ完了。
Line 71: Line 71:
  * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.

 * Report of work (*:responsible person)
  * Alignment: *Izumi
   * X-armまでリカバーした。
   * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
    * GASは真空槽を開けずに直せる範囲を超えている模様。
    * PR3で100uradのオーダーでずれていた。
    * Oplevの範囲をすでに超えてしまっている。


  * PLC at Yend: Aso
   * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。

  * Marionet Oplev: Akutsu
   * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
  * BS:神津、Enzo
   * リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。
Line 90: Line 76:
  * Alignment: *Izumi
   * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。
  * Vacuum
   * 昨日午後から延期になって、本日朝真空引き予定
    * ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川
    * コントロールルーム: 和泉、奥富
   * Check listによる最終確認
Line 93: Line 82:
  * Marionet Oplev: Akutsu
   * QPDの信号を確認する予定。

 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F
 * Laser hazard: 今日は午前はPSLのみ。午後からIMMT。
Line 101: Line 85:
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.

  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.
Line 110: Line 86:
   * 1/24,25 leak check.    * 1/24: Pump down.
   * 1/25: Turbo pump on.
Line 113: Line 90:
   * 1/29 Cooling start    * 1/29,30 leak check.

  * Week of 2/5
   * 2/5
Cooling start.
Line 116: Line 97:
   * EX のポラリティーが反転していた。回路の問題か?
   * 真空曹を開けてPR2とPR3を直すかどうか。
  * Network cableの整理
  * ピコモーターの反応がなくなる。
Line 129: Line 110:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 139: Line 121:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 146: Line 128:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/23 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Pump down
    • 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/23(Tue.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • IOO: 苔山
      • 精密空調が入って、温度が安定した。
    • Vacuum
      • Oplevがヒートリンクで遮られていた。
      • Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。
        • 再度戻り光も確認した。
      • 真空引きの準備がほぼ完了。
    • BS:神津、Enzo

      • リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。
  • Work plan (*:responsible person)
    • Vacuum
      • 昨日午後から延期になって、本日朝真空引き予定
        • ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川
        • コントロールルーム: 和泉、奥富
      • Check listによる最終確認
  • Laser hazard: 今日は午前はPSLのみ。午後からIMMT。
  • Weekly
    • Week of 1/22
      • 1/24: Pump down.
      • 1/25: Turbo pump on.
    • Week of 1/29
      • 1/29,30 leak check.
    • Week of 2/5
      • 2/5 Cooling start.
  • Issues
    • Network cableの整理
    • ピコモーターの反応がなくなる。

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1