Differences between revisions 246 and 270 (spanning 24 versions)
Revision 246 as of 2018-01-12 09:52:57
Size: 8451
Comment:
Revision 270 as of 2018-01-26 09:11:21
Size: 7998
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/1/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/1/23 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
Line 26: Line 20:
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)   * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)

 * Beam leading to REFP port
  * *Izumi
Line 60: Line 57:
2017/1/12(Fri.) 2017/1/26(Fri.)
Line 62: Line 59:
 * Remote participants by educe: None

 * Affect of short power failure
  * VIS
   * EX のポラリティーが反転していた。瞬停と関係あるかは不明。

  * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi
   * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC.

  * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now.
 * Remote participants by eZuce:
Line 74: Line 62:
  * Alignment: *Izumi
   * X-armまでリカバーした。
   * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。
    * GASは真空槽を開けずに直せる範囲を超えている模様。
    * PR3で100uradのオーダーでずれていた。
    * Oplevの範囲内には入っているが、PRの曲率によりゼロ点意味をなさなくなっている。

  * Vacuum
   * ターボポンプを入れた。

  * Alignment
   * Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。
   
  * AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada
   * k1iy0への電源ケーブルの仕上げ。
   * IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。

 * Work plan (*:responsible person)
  * 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。
  * Alignment: Oplevのセンタリング。
Line 82: Line 78:
  * PLC at Yend: Aso
   * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。
 * Laser hazard: Upstream of IMMT line
Line 85: Line 80:
  * Marionet Oplev: Akutsu
   * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。
 * Weekly
  * Week of 1/22
   * 1/24: Pump down.
   * 1/25: Turbo pump on.

  * Week of 1/29
   * 1/29,30 leak check.
   * 1/30 Opening ETMY gate valve.

  * Week of 2/5
   * 2/5 Cooling start.
Line 89: Line 93:
 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。

  * Marionet Oplev: Akutsu
   * QPDの信号を確認する予定。

 
 * Laser hazard area
  * Behind of BS and SR line and Yend 1F

 * Weekly
  * Week of 1/8
   * 1/11, 12: Re-alignment for IFO.
   * 1/13, 14: Damping for ETMY.

  * Week of 1/15
   * IOO works.
   * 1/19: Pump down.

  * Week of 1/22
   * 1/24,25 leak check.

  * Week of 1/29
   * 1/29 Cooling start
Line 116: Line 94:
   * EX のポラリティーが反転していた。回路の問題か?
   * 真空曹を開けてPR2とPR3を直すかどうか。
  * Network cableの整理
  * ピコモーターの反応がなくなる。
Line 129: Line 107:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 139: Line 118:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 146: Line 125:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/23 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Pump down
    • 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/26(Fri.)

  • Remote participants by eZuce:
  • Report of work (*:responsible person)
    • Vacuum
      • ターボポンプを入れた。
    • Alignment
      • Yaw方向に何度かジャンプが見られて、mradのオーダーで動いていることがわかった。Oplevの線形範囲内からは出ていたが、センサー面内には入っていたので朝の時点でセンターまで戻した。
    • AEL, DGS: Yamamoto, Miyakawa, Awai, Hayakawa, Tamori, Nakada
      • k1iy0への電源ケーブルの仕上げ。
      • IO chassis用の光ケーブルを12本計算機室からスロープ上部を通過するまで配線。
  • Work plan (*:responsible person)
    • 雪のため、できるだけ入坑を避ける。本日は特にコミッショニング入坑は関係はなし。
    • Alignment: Oplevのセンタリング。
  • Laser hazard: Upstream of IMMT line
  • Weekly
    • Week of 1/22
      • 1/24: Pump down.
      • 1/25: Turbo pump on.
    • Week of 1/29
      • 1/29,30 leak check.
      • 1/30 Opening ETMY gate valve.
    • Week of 2/5
      • 2/5 Cooling start.
  • Issues
    • Network cableの整理
    • ピコモーターの反応がなくなる。

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)