Line 11: Line 11:
2017/1/16 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}}
2017/1/23 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}
Line 18: Line 18:
 * Re alignment
  * 1/12 *Izumi

 * Damping for ETMY
  * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
  * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
Line 26: Line 20:
  * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)   * 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)

 * Beam leading to REFP port
  * *Izumi
Line 60: Line 57:
2017/1/17(Wed.) 2017/1/23(Tue.)
Line 65: Line 62:
  * Alignment: *Izumi
   * Buffle PDがETMYにインストールされた。真空槽内はケーブリングも含めて完了。
   * 読み出し回路を用意している。ケーブルなどと合わせてほぼ準備が整った。計算機側の準備もOK。接続を待つのみ。
  * IOO: 苔山
   * 精密空調が入って、温度が安定した。
Line 69: Line 65:
 * IOO
  * PSL上のパワーを変更して、メインパワーを1Wまで上げた。実際には干渉計直前で蹴っているので、干渉計側には今まで通り100mW程度が入っている。メインパワーの変動が数十%と大きくなってしまっている。今の所変動の原因は不明。
  * Vacuum
   * Oplevがヒートリンクで遮られていた。
   * Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。
    * 再度戻り光も確認した。
   * 真空引きの準備がほぼ完了。

  * BS:神津、Enzo
   * リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。
Line 73: Line 76:
  * Alignment: *Izumi
   * 午前中EYでの回路接続。夕方から全域をハザートエリアにして、アラインメント作業。
  * Vacuum
   * 昨日午後から延期になって、本日朝真空引き予定
    * ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川
    * コントロールルーム: 和泉、奥富
   * Check listによる最終確認
Line 76: Line 82:
   * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.  * Laser hazard: 今日は午前はPSLのみ。午後からIMMT。
Line 80: Line 85:
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting
   * 1/19: Pump down.
Line 87: Line 86:
   * 1/24,25 leak check.    * 1/24: Pump down.
   * 1/25: Turbo pump on.
Line 90: Line 90:
   * 1/29 Cooling start    * 1/29,30 leak check.

  * Week of 2/5
   * 2/5
Cooling start.
Line 95: Line 98:
  * ピコモーターの反応がなくなる。
Line 106: Line 110:
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
Line 116: Line 121:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 123: Line 128:
 * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])  * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/23 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Pump down
    • 1/24 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/23(Tue.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • IOO: 苔山
      • 精密空調が入って、温度が安定した。
    • Vacuum
      • Oplevがヒートリンクで遮られていた。
      • Payloadの向きが10mradくらい、BFが逆向きに5mradくらいツイストした。BFを戻したらOplevも戻った。
        • 再度戻り光も確認した。
      • 真空引きの準備がほぼ完了。
    • BS:神津、Enzo

      • リアルタイムモデルを改良中。チャンネル追加や、コモンフィルターの整備。
  • Work plan (*:responsible person)
    • Vacuum
      • 昨日午後から延期になって、本日朝真空引き予定
        • ETMY立会い: 木村、鈴木、都丸、横澤、高橋、宮川
        • コントロールルーム: 和泉、奥富
      • Check listによる最終確認
  • Laser hazard: 今日は午前はPSLのみ。午後からIMMT。
  • Weekly
    • Week of 1/22
      • 1/24: Pump down.
      • 1/25: Turbo pump on.
    • Week of 1/29
      • 1/29,30 leak check.
    • Week of 2/5
      • 2/5 Cooling start.
  • Issues
    • Network cableの整理
    • ピコモーターの反応がなくなる。

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)