Line 3: | Line 3: |
== Working people == | |
Line 5: | Line 4: |
* 10/12 *苔山、和泉、榎本、中野、鍛治、三代、新井 * 10/13 苔山、*横澤、榎本、中野、三代、新井 . * 10/16 横澤、井上、榎本、*中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/17 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 . * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か |
== Task list == |
Line 20: | Line 6: |
. * 責任者 | * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] |
Line 22: | Line 10: |
== Schedule == 2017/1/18 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} ----- == Working people assignment == * *: responsible person * Pump down * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) * Beam leading to REFP port * *Izumi {{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} ----- <<Anchor(Meetings)>> |
|
Line 26: | Line 50: |
<<Anchor(MorningMeetings)>> | |
Line 29: | Line 54: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 32: | Line 57: |
2017/10/13(Fri) | 2017/1/19(Thur.) |
Line 34: | Line 59: |
* Daily * 作業人員(*:責任者) * MIF: 苔山、*横澤、榎本、中野、三代、新井 |
* Remote participants by educe: None |
Line 38: | Line 61: |
* Laser hazard * PSLから15mWで、IMC入り口で10mW、PRM以降は1mW程度。今日のPR2の作業によって来週エンドをハザードエリアにするか決める。 * 来週以降も2mWでいこうと思っている。 |
* Report of work (*:responsible person) * Vacuum * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY. |
Line 42: | Line 65: |
* 作業 * PR2からの反射光が1m先で数cm下がっていた。10mradのオーダー。PR2が水平かどうかの確認。する予定。(苔山) * BS: ファーストコンタクトを今日剥がす。あとはブレッドボードの高さ調整と、リモートコントロールが必要。 |
* IOO: *Kokeyama * 1WがMCに入った。 * Alignment: *Izumi * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。 * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。 * ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。 * Work plan (*:responsible person) * Alignment: *Izumi * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。 * 11時頃からレーザーハザードを全域に変更してアラインメント作業。 * 真空引きの最終判断は月曜日にする。 * チェックリスト最終確認。 * φ800フランジを閉める。 * Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM. |
Line 47: | Line 87: |
* 今週の目標はPR3からの光がBSまで届くこと。 * 問題点など * PR2の反射光を解決する必要がある。来週以降の遅れを生む可能性あり。 |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * Week of 1/22 * 1/23: Pump down. * 1/24: Turbo pump on. * Week of 1/29 * 1/29,30 leak check. * Week of 2/5 * Cooling start. * Issues * Network cableの整理 |
Line 55: | Line 111: |
<<Anchor(WeeklyMeetings)>> | |
Line 57: | Line 114: |
* Location: Meeting room at Hokum Kaikan, or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 67: | Line 135: |
* Meeting about SR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] |
Line 76: | Line 150: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/18 updated
Working people assignment
- *: responsible person
- Pump down
- 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/19(Thur.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Vacuum
- Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
- IOO: *Kokeyama
- 1WがMCに入った。
- Alignment: *Izumi
- ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
- Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
- ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。
- Vacuum
- Work plan (*:responsible person)
- Alignment: *Izumi
- EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
- 11時頃からレーザーハザードを全域に変更してアラインメント作業。
- 真空引きの最終判断は月曜日にする。
- チェックリスト最終確認。
- φ800フランジを閉める。
- Alignment: *Izumi
- Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM.
- Weekly
- Week of 1/15
- 1/15~ baffle PD installation
- 1/16~ IOO works.
- 1/17: Vacuum check meeting
- Week of 1/22
- 1/23: Pump down.
- 1/24: Turbo pump on.
- Week of 1/29
- 1/29,30 leak check.
- Week of 2/5
- Cooling start.
- Week of 1/15
- Issues
- Network cableの整理
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)