== Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} ----- |
|
Line 4: | Line 17: |
* MIF + VIS | * *: responsible person * Re alignment * 1/11 *Izumi * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 6: | Line 29: |
* 10/16 横澤、井上、榎本、*中野、麻生、Fabian、Enzo、平田、神津、新井、正田 * 10/17 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 . * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か |
{{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == |
Line 18: | Line 34: |
. * 責任者 | * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} |
Line 20: | Line 48: |
<<Anchor(Meetings)>> |
|
Line 24: | Line 54: |
<<Anchor(MorningMeetings)>> | |
Line 27: | Line 58: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 30: | Line 61: |
2017/10/16(Mon) | 2017/1/11(Thrs.) |
Line 32: | Line 63: |
* Daily * 作業人員(*:責任者) * MIF+VIS: 横澤、榎本、*中野、麻生、Fabian、Enzo、平田、神津、新井、正田 (PHS: V-7, V-12) |
* Remote participants by educe: None |
Line 36: | Line 65: |
* Laser hazard * PSLから15mWで、IMC入り口で10mW、PRM以降は1mW程度。今日のPR2の作業によって来週エンドをハザードエリアにするか決める。 * 今週もPR2の作業が終わるまでは2mW未満。 |
* Report of work (*:responsible person) |
Line 40: | Line 67: |
* 作業 * PR2が5mradほどピッチに傾いることがOplev及びメインビームで確認できた。同様にPR3も3mradピッチに傾いていた。 * 午後からPR2の再アラインメント。午前中はIMMTの取り回しを確認。 * BS: ファーストコンタクトをは外れた。ブレッドボードの高さ変更を今週中にする。 * BSのOplevはないがチェックする必要がある。 |
* Work plan (*:responsible person) * Alignment: *Izumi * Oplev, Re-alignment * Check of PLC at Yend for connection to measurement tools: Aso * Marionet Oplev: Akutsu * Laser hazard area * Behind of BS and SR line and Yend 1F |
Line 47: | Line 79: |
* 10/9の目標はPR3からの光がBSまで届くこと。->10/16の週の前半に延期 * 問題点など * PR2の反射光を解決する必要がある。2日ほどはかかるので少し遅れが発生している。 |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. * Week of 1/15 * IOO works. * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. * Week of 1/29 * 1/29 Cooling start * Issues |
Line 55: | Line 100: |
<<Anchor(WeeklyMeetings)>> | |
Line 57: | Line 103: |
* Location: Meeting room at Hokum Kaikan, or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||5||2017/10/10||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]|| ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 68: | Line 123: |
* Meeting about SR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) | * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] |
Line 77: | Line 136: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/10 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/11 *Izumi
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/11(Thrs.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Work plan (*:responsible person)
- Alignment: *Izumi
- Oplev, Re-alignment
- Check of PLC at Yend for connection to measurement tools: Aso
- Marionet Oplev: Akutsu
- Alignment: *Izumi
- Laser hazard area
- Behind of BS and SR line and Yend 1F
- Weekly
- Week of 1/8
- 1/11, 12: Re-alignment for IFO.
- 1/13, 14: Damping for ETMY.
- Week of 1/15
- IOO works.
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/8
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)