== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/1/18 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}}


-----
Line 4: Line 17:
 * MIF + VIS  * *: responsible person

 * Pump down
  * 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)

 * Beam leading to REFP port
  * *Izumi
Line 6: Line 25:
  * 10/18 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/19 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  .
  * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==
Line 16: Line 30:
 . * 責任者  * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
Line 18: Line 44:

<<Anchor(Meetings)>>
Line 22: Line 50:
<<Anchor(MorningMeetings)>>
Line 25: Line 54:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 28: Line 57:
2017/10/17(Tue) 2017/1/19(Thur.)
Line 30: Line 59:
 * Daily
  * 作業人員(*:責任者)
   * MIF+VIS: *和泉、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井、正田、井上、灰野、横澤 (PHS: V-3(榎本), V-7, V-12(横澤))
 * Remote participants by educe: None
Line 34: Line 61:
  * Laser hazard
   * PSLから15mWで、IMC出口で10mW、PRM以降は1mW程度。
   * 今日のある時点からハザードエリアが中央エリアの1階(機械室は除く)になる。
   * 中央エリアにいる作業者全員、Yエンドの安全責任者、(必要ならYアームにいる安全責任者も)にアナウンス。
   * 中央実験室にいる人はそれ以降全員保護メガネの着用をお願いします。
   * Yエンド、Yアームに行く方は、最初にPRMラインの安全パネルの前に置いてある保護メガネを各自1個ずつ持っていって下さい。そして、もし、中央エリアがハザードエリアになった場合は、帰りなどに中央エリアを通る際は保護メガネの着用をお願いします。保護メガネは、前室の入り口横に移動される保護メガネ台に返してください。
   * Xエンドに行く方は保護メガネは必要ありません。
 * Report of work (*:responsible person)
  * Vacuum
   * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
Line 42: Line 65:
  * 作業
   * アラインメント(中野)
    * IMMT1の中段マスの磁石をピコモーターを動かして外した。タワー全体を回したということ。PR2まで光が通った。トラバーサーを動かしてPR3まで光が通った。
    * PR3のピッチの再アラインメントでOSEMが当たってしまったので、OSEMを動かす。
    * BSも3mradくらいピッチ方向にずれている模様。
   * BS: ハードウェア的な仕事は完了した。(Fabian)
 * 両エンドにPDケーブルとも完了。信号もDAQで見えた。(井上)
 * GigEカメラをセットアップする。->麻生+ケーブル張りを誰か
  * IOO: *Kokeyama
   * 1WがMCに入った。

  * Alignment: *Izumi
   * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
   * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
   * ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。

 * Work plan (*:responsible person)
  * Alignment: *Izumi
   * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
   * 11時頃からレーザーハザードを全域に変更してアラインメント作業。


  * 真空引きの最終判断は月曜日にする。
   * チェックリスト最終確認。
   * φ800フランジを閉める。

 
 * Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM.
Line 52: Line 87:
  * 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。
 * 問題点など
  * PR2, PR3のミスアラインメントを解決する必要がある。2日ほどはかかるので少し遅れが発生している。
  * コーチフィルターが不調。
  * PR3の前室のクリーンブースのシートが落ちてしまっている。->中田
  * Week of 1/15
   * 1/15~ baffle PD installation
   * 1/16~ IOO works.
   * 1/17: Vacuum check meeting

  * Week of 1/22
   * 1/23: Pump down.
   * 1/24: Turbo pump on.

  * Week of 1/29
   * 1/29,30 leak check.

  * Week of 2/5

   * Cooling start.


 * Issues
  * Network cableの整理
Line 62: Line 111:
<<Anchor(WeeklyMeetings)>>
Line 64: Line 114:
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
Line 69: Line 129:
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 75: Line 135:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
Line 76: Line 141:
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
Line 84: Line 150:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule

2017/1/18 updated KAGRA/Commissioning/Commissioning_schedule_20180123.png


Working people assignment

  • *: responsible person
  • Pump down
    • 1/23 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/1/19(Thur.)

  • Remote participants by educe: None
  • Report of work (*:responsible person)
    • Vacuum
      • Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY.
    • IOO: *Kokeyama
      • 1WがMCに入った。
    • Alignment: *Izumi
      • ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。
      • Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。
      • ETMYからの戻り光をリサージュで一晩振ったが見つかっていない。スリットを再び入れる予定。
  • Work plan (*:responsible person)
    • Alignment: *Izumi
      • EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。
      • 11時頃からレーザーハザードを全域に変更してアラインメント作業。
    • 真空引きの最終判断は月曜日にする。
      • チェックリスト最終確認。
      • φ800フランジを閉める。
  • Laser hazard: All area will be changed to after 11AM. Nakada-san will change the border by 11AM.
  • Weekly
    • Week of 1/15
      • 1/15~ baffle PD installation
      • 1/16~ IOO works.
      • 1/17: Vacuum check meeting
    • Week of 1/22
      • 1/23: Pump down.
      • 1/24: Turbo pump on.
    • Week of 1/29
      • 1/29,30 leak check.
    • Week of 2/5
      • Cooling start.
  • Issues
    • Network cableの整理

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents