4730
Comment:
|
8443
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
== Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/1/16 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} ----- |
|
Line 4: | Line 17: |
* MIF + VIS | * *: responsible person * Re alignment * 1/12 *Izumi * Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 6: | Line 28: |
* 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井 . * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か |
{{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == |
Line 14: | Line 33: |
. * 責任者 | * Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 }}} |
Line 16: | Line 47: |
<<Anchor(Meetings)>> |
|
Line 20: | Line 53: |
<<Anchor(MorningMeetings)>> | |
Line 23: | Line 57: |
* Location: Control room, or educe | * Location: Control room, or eZuce |
Line 26: | Line 60: |
2017/10/20(Fri) | 2017/1/18(Thur.) |
Line 28: | Line 62: |
* Daily * 作業人員(*:責任者) * MIF+VIS: *和泉、榎本、新井、正田、井上、灰野、横澤、土田、Fabian、Enzo、平田 (PHS: V-3(榎本), V-7(), V-12(横澤)) |
* Remote participants by educe: None |
Line 32: | Line 64: |
* Laser hazard * PSL直後で120mW、IMC出口で1000mW程度、PRM以降は10mW程度。 * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。 * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを使い通過して下さい。メガネはそのまま持って行って、帰りに中央エリアを通る際は再び保護メガネの着用をお願いします。 * EXA, EYAの真空槽まわりで作業する人は保護メガネをかけください。そばを通るだけの方は保護メガネは必要ありません。 |
* Report of work (*:responsible person) * Alignment: *Izumi * EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。 * ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。 * CryopayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。 |
Line 38: | Line 70: |
* 作業 * アラインメント(和泉) * 日に日にアラインメントがずれているようだったので、Oplevをキャリブレーションし直した。IMMTなどファクター3とか10間違っていた。 * Xエンドまで光が通った。直接光かどうかはまだ不明。PDのゲイン調整と、センサーカードで確認予定。 * PR2が100urad程度揺れている模様。 * X/Y end * EXAにカメラがインストールされた。 * 200HzのノイズはLEDと判明。リモートでオンオフできないので、現在は消してある。 * EYAにもビューポーを設置した。EYAにもカメラをつけるかどうか検討する。(井上) |
* Work plan (*:responsible person) * Alignment: *Izumi * 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。 * CryopayloadのVisual inspection. * φ800フランジは今日は開けておく。明日閉める。 * IOO: *Kokeyama * 1WをMCに入れる。 * 真空引き判断 * チェックリスト最終確認。 * 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。 * おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。 * Cryostatのタッチがないかを確認。 * φ800フランジを閉める。 * Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment. |
Line 49: | Line 90: |
* 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。->ほぼ目標達成。 * 10/23の週: Yエンドに光を送る。 |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * 1/19: Pump down. |
Line 52: | Line 96: |
* 問題点など * コーチフィルターが不調。 |
* Week of 1/22 * 1/24,25 leak check. * Week of 1/29 * 1/29 Cooling start * Issues * Network cableの整理 * Cryostatがタッチしている可能性あり。 * ビームアラインメントの最終確認が時間的にぎりぎり。 |
Line 59: | Line 112: |
<<Anchor(WeeklyMeetings)>> | |
Line 61: | Line 115: |
* Location: Meeting room at Hokum , or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| |
Line 66: | Line 129: |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 72: | Line 135: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) |
|
Line 73: | Line 140: |
* [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] | |
Line 81: | Line 149: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/16 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/18(Thur.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Alignment: *Izumi
- EYのBaffle PDの回路を接続して準備が完了した。18時頃からBSからETMY方向にビームを飛ばしリサージュで振り始めた。
- ビームはまだ確認できていない。ゲインが500倍くらい低かったせい。再度ゲインを上げて試す。
- CryopayloadでもYawが動かないことがあったので、当たっている可能性があることがわかった。
- Alignment: *Izumi
- Work plan (*:responsible person)
- Alignment: *Izumi
- 午後3時か4時頃から、再度ゲインを上げてETMYでの確認を試す。
- CryopayloadのVisual inspection.
- φ800フランジは今日は開けておく。明日閉める。
- IOO: *Kokeyama
- 1WをMCに入れる。
- 真空引き判断
- チェックリスト最終確認。
- 最速で今日の夕方ETMYで光が見えて、うまくいけばBSでもすぐに見える。
- おそらくビームがBSまで返って届いているかの判断は明日朝になりそう。ただしリモートで全てできることなので、ビーム確認なしで真空引きをする可能性もある。
- Cryostatのタッチがないかを確認。
- φ800フランジを閉める。
- Alignment: *Izumi
- Laser hazard: Upstream of IMM line in the daily time. All area after evening for the alignment.
- Weekly
- Week of 1/15
- 1/15~ baffle PD installation
- 1/16~ IOO works.
- 1/17: Vacuum check meeting
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/29
- 1/29 Cooling start
- Week of 1/15
- Issues
- Network cableの整理
- Cryostatがタッチしている可能性あり。
- ビームアラインメントの最終確認が時間的にぎりぎり。
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)