Differences between revisions 185 and 289 (spanning 104 versions)
Revision 185 as of 2017-12-07 09:39:17
Size: 7098
Comment:
Revision 289 as of 2018-02-07 09:24:03
Size: 8366
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/2/5 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}}
Line 17: Line 17:
* 責任者  * *: responsible person

 * Beam leading to REFP port
  * *Izumi
Line 19: Line 22:

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
 * ETMYアラインメント
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
 

Line 62: Line 54:
2017/12/7(Thur.) 2017/2/7(Wed.)
Line 64: Line 56:
 * Daily
  * 作業 (*:責任者)
   * 位置測定: *内山、寺田(V-11, 2831)
    * 昨日は準備。鏡の中心を測った。今日はビームの位置を比較確認。
 * Remote participants by eZuce: None
Line 69: Line 58:
   * アラインメント: 和泉(2829)
    * レーザー不調のため、アラインメントはそれほど進展がなかった。
    * レーザーはFSSがロックしなかった。AOMのドライバーが不調だったが、結局電源のバナナピンの接触不良が原因であることが判明。MCも復帰した。
    * ピコモーターのジョイスティックをつなげるところを間違えて、SMT1のピッチを動かしてしまった。そのためでFIを通っていない時間が存在する。FI後のQPDで確認しながら復帰。
    * 現在ETMXまでは光がいっている。
 * Report of work (*:responsible person)
  * Alignment and Vibration Isolation: Izumi, Okutomi
   * Searching optimal position of IP of ETMY was successfully done. Stiffness is almost the same as what was measured in the air. But Q is still not so high. Still something lower stage might be hitting somewhere.
  * Mirror view by Team also moved by 6mm order! It means that the calibration can be wrong by 25 times.
  * The result of fine tuning showed 1mm off to -x direction.

 * Vacuum: Kimura
  * Another leakage was found 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.

 * Work plan (*:responsible person)

  * Cooling: Kimura, Suzuki, Yokozawa
   * We will start cooling around 11AM.

  * WAB cooling test: Akutsu
   * Temperature monitors are being prepared.
   * Oplev is ready.

 * Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.

 * Weekly
  * Week of 2/5
   * Finding causes of ETMY trouble.
    * Vent might be needed if ETMY is touching somewhere.
    * Cooling also will be delayed for 2weeks or so.
Line 76: Line 85:
   * Type B: *Mark、平田、Fabian
    * 新しいマトリックスがうまくいって、キャリブレーションがとれた。そのためダンピングも改良できそう。

   * Type A: *高橋(2637)、奥富
    * EYCのペイロードがBS方向に1cmずれていることが一昨日の時点で判明。ヒートリンクが引っ剝いている可能性がある。150gGの力でこれくらいのずれになる見込み。
    * トップは2mm程度のずれで、こちらは問題なさそう。

   * Cry: 宮本
    * actuatorのテストなどする予定。できれば伝達関数測定までしたい。

   * AEL: MC WFSで問題のあったI&Q demodulatorの3chテスト結果は、特に問題ないというものだった。よって坑内で何がダメだったのかは不明。

  * Laser hazard
   * SRラインより奥。

 * Weekly
  * 12/4の週
   * Type Aダンピングテスト。
   * メインビームの再アラインメント。
   * 月、火にIYC、IXCでの真空作業がある。
   * 12/6,7: PR-BS相対位置測

  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。


 * 問題点など
  * PR-BS相対位置測定後、EXでの再位置測定が必要か?
 * Issues
  * IP drifted 2mm in the air, and another 2mm when pump down.
Line 116: Line 98:
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 122: Line 111:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 129: Line 118:
 * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/2/5 updated KAGRA/Commissioning/Commissioning_schedule_20180206.png


Working people assignment

  • *: responsible person
  • Beam leading to REFP port
    • *Izumi



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/2/7(Wed.)

  • Remote participants by eZuce: None
  • Report of work (*:responsible person)
    • Alignment and Vibration Isolation: Izumi, Okutomi
      • Searching optimal position of IP of ETMY was successfully done. Stiffness is almost the same as what was measured in the air. But Q is still not so high. Still something lower stage might be hitting somewhere.
    • Mirror view by Team also moved by 6mm order! It means that the calibration can be wrong by 25 times.
    • The result of fine tuning showed 1mm off to -x direction.
  • Vacuum: Kimura
    • Another leakage was found 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.
  • Work plan (*:responsible person)
    • Cooling: Kimura, Suzuki, Yokozawa
      • We will start cooling around 11AM.
    • WAB cooling test: Akutsu
      • Temperature monitors are being prepared.
      • Oplev is ready.
  • Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.
  • Weekly
    • Week of 2/5
      • Finding causes of ETMY trouble.
        • Vent might be needed if ETMY is touching somewhere.
        • Cooling also will be delayed for 2weeks or so.
  • Issues
    • IP drifted 2mm in the air, and another 2mm when pump down.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools