6438
Comment:
|
8394
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/11/28 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}} |
2017/2/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/11 * 12/12 和泉 * 12/13 和泉 * 12/14 和泉、長野 * 12/15 和泉、長野、榎本 * GigEカメラセット * 12/11 * 12/12 * 12/13 * 12/14 * 12/15 * BS PDセット * 12/11 * 12/12 横澤 * 12/13 横澤 * 12/14 * 12/15 |
* Beam leading to REFP port * *Izumi |
Line 73: | Line 54: |
2017/12/11(Mon.) | 2017/2/7(Wed.) |
Line 75: | Line 56: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: None |
Line 78: | Line 58: |
* アラインメント: * 現在Xエンドまで通っている。明日、明後日でEYAに通す。 |
* Report of work (*:responsible person) * Alignment and Vibration Isolation: Izumi, Okutomi * Searching optimal position of IP of ETMY resulted that the stiffness (DC response level) is the same as what it was measured in the air. Still something at lower stage might be hitting somewhere. * Mirror view by Tcam also moved by 6mm order! It means that the calibration of LVDT can be wrong by factor of 25. * The result of fine tuning showed 1mm off to -x direction. |
Line 81: | Line 64: |
* Type B: *Mark、Enzo, 神津、正田 * 今日も引き続き制御系のチェックをする。 |
* Vacuum: Kimura * Another leakage was found with 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling. |
Line 84: | Line 67: |
* Type A: 午後から*高橋(2637)、奥富、宮本 * actuatorのテストなどの続き。 * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。 |
* Work plan (*:responsible person) |
Line 88: | Line 69: |
* PD設置: 横澤 * PDをYendからBSに持ってくる。金曜まででケーブルなどの準備はほぼできたので、明日か明後日にIYAからBSにPDを移動。BSテーブルでのマウント方法を検討する必要がある。 |
* Cooling: Kimura, Suzuki, Yokozawa * We will start cooling around 11AM. * Alignment: Izumi, Miyakawa * Oplev of ETMY will be monitored at the control room, and misalignment will be restored remotely during the cooling. * WAB cooling test: Akutsu * Temperature monitors are being prepared. * Oplev is ready. * Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area. * Weekly * Week of 2/5 * 2/7 Cooling. |
Line 92: | Line 86: |
* Laser hazard * SRラインより奥。 * Weekly * 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 * 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * BSテーブルにPDを置けるかどうか。 * Eendの遮蔽板をいつ開けるか。 * 真空引きの最終確認。 |
* Issues * IP drifted 2mm in the air, and another 2mm when pump down. |
Line 121: | Line 99: |
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || |
|
Line 127: | Line 112: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 134: | Line 119: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/7(Wed.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment and Vibration Isolation: Izumi, Okutomi
- Searching optimal position of IP of ETMY resulted that the stiffness (DC response level) is the same as what it was measured in the air. Still something at lower stage might be hitting somewhere.
- Mirror view by Tcam also moved by 6mm order! It means that the calibration of LVDT can be wrong by factor of 25.
- The result of fine tuning showed 1mm off to -x direction.
- Alignment and Vibration Isolation: Izumi, Okutomi
- Vacuum: Kimura
- Another leakage was found with 1e-8 order (2 order of magnitude larger than other two). We leave it anyway and we will start cooling.
- Work plan (*:responsible person)
- Cooling: Kimura, Suzuki, Yokozawa
- We will start cooling around 11AM.
- Alignment: Izumi, Miyakawa
- Oplev of ETMY will be monitored at the control room, and misalignment will be restored remotely during the cooling.
- WAB cooling test: Akutsu
- Temperature monitors are being prepared.
- Oplev is ready.
- Cooling: Kimura, Suzuki, Yokozawa
- Laser hazard: PSL. Green will be used all the day, then the center up to PR3 will be the hazard area.
- Weekly
- Week of 2/5
- 2/7 Cooling.
- Week of 2/5
- Issues
- IP drifted 2mm in the air, and another 2mm when pump down.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools