6680
Comment:
|
8368
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/11 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}} |
2017/2/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/11 * 12/12 和泉 * 12/13 和泉 * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/11 * 12/12 * 12/13 * 12/14 * 12/15 * BS PDセット * 12/11 * 12/12 横澤 * 12/13 横澤 * 12/14 * 12/15 |
* Beam leading to REFP port * *Izumi |
Line 73: | Line 54: |
2017/12/11(Mon.) | 2017/2/6(Tue.) |
Line 75: | Line 56: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: Takahashi |
Line 78: | Line 58: |
* アラインメント: * 現在Xエンドまで通っている。明日、明後日でEYAに通す。 |
* Report of work (*:responsible person) * Alignment and Vibration Isolation: Izumi, Okutomi * BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started. * IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi) * ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low. |
Line 81: | Line 64: |
* Type B: *Mark、Enzo, 神津、正田 * 今日も引き続き制御系のチェックをする。 |
* Work plan (*:responsible person) |
Line 84: | Line 66: |
* Type A: 午後から*高橋(2637)、奥富、宮本 * actuatorのテストなどの続き。 * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。 |
* Alignment and Vibration Isolation: *Izumi * We can move moving masses of BF, or IPs of yaw to check TF can be recovered. * We will play one more day under vacuum. |
Line 88: | Line 70: |
* PD設置: 横澤 * PDをYendからBSに持ってくる。金曜まででケーブルなどの準備はほぼできたので、明日か明後日にIYAからBSにPDを移動。BSテーブルでのマウント方法を検討する必要がある。 |
* Type A: *Yokozawa * RT model of Type A will be separated into cryopayload and tower. * Type B * SR assembly continues. * Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area. * Weekly * Week of 2/5 * Finding causes of ETMY trouble. * Evacuation might be needed if ETMY is touching somewhere. * Cooling also will be delayed for 2weeks or so. |
Line 92: | Line 85: |
* Laser hazard * SRラインより奥。 * Weekly * 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 * 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * BSテーブルにPDを置けるかどうか。 * Eendの遮蔽板をいつ開けるか。 * 真空引きの最終確認。 |
* Issues * IP drifted 2mm in the air, and another 2mm when pump down. |
Line 121: | Line 98: |
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 128: | Line 111: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 135: | Line 118: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/6(Tue.)
- Remote participants by eZuce: Takahashi
- Report of work (*:responsible person)
- Alignment and Vibration Isolation: Izumi, Okutomi
- BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started.
- IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi)
- ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low.
- Alignment and Vibration Isolation: Izumi, Okutomi
- Work plan (*:responsible person)
- Alignment and Vibration Isolation: *Izumi
- We can move moving masses of BF, or IPs of yaw to check TF can be recovered.
- We will play one more day under vacuum.
- Type A: *Yokozawa
- RT model of Type A will be separated into cryopayload and tower.
- Type B
- SR assembly continues.
- Alignment and Vibration Isolation: *Izumi
- Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area.
- Weekly
- Week of 2/5
- Finding causes of ETMY trouble.
- Evacuation might be needed if ETMY is touching somewhere.
- Cooling also will be delayed for 2weeks or so.
- Finding causes of ETMY trouble.
- Week of 2/5
- Issues
- IP drifted 2mm in the air, and another 2mm when pump down.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)