7219
Comment:
|
8101
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/11 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171212.png||width=1200}} |
2017/1/30 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/11 * 12/12 和泉 * 12/13 和泉 * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/11 * 12/12 * 12/13 * 12/14 * 12/15 * BS PDセット * 12/11 * 12/12 横澤 * 12/13 横澤 * 12/14 * 12/15 |
* Beam leading to REFP port * *Izumi |
Line 73: | Line 54: |
2017/12/12(Tue.) | 2017/1/31(Wed.) |
Line 75: | Line 56: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: Miyoki |
Line 78: | Line 58: |
* アラインメント: *和泉、苔山、野替 * 今日午後から、Xエンドのビームの確認、その後EYAに通す予定。PR2,3のOplevのダンピングをしたい。 * 現在PR3は固定してあるが、Phase1の間は固定したままで残すことを考えている。 * ワイヤーのテンションをきちんと張って落ち着かせる方法をVIRGOの人から聞いたので、とりあえずSRで試してみる予定。 |
* Report of work (*:responsible person) * Vacuum: 木村 * Leakが三箇所でみつかった。一つは増し締めで解決。もう二つは高真空でのリークなので、今回はそのまま。 * 真空の判断でゲートバルブを開ける。 |
Line 83: | Line 63: |
* Type A: *高橋、奥富、宮本 * Oplevのキャリブレーションについてklogに報告があった。どれだけ進んでいるのか要確認。 * Yエンドの遮蔽板を開けるのが木村さんがくる13日になりそう。アルミホイルで塞ぐ方法もあるので、基本的に開ける方向で進める。 |
* Alignment: 宮川 * 1日の揺れが線形領域内の半分程度に収まった。Excitationが以前収まらない。 |
Line 87: | Line 66: |
* PD設置: 横澤 * 明日PDをYendからBSに持ってくることになりそう。BSテーブルでのマウント方法を検討する必要がある。 |
* Work plan (*:responsible person) * Vacuum: *木村、上田、宍戸、高橋 * 今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。 * gate valveを開ける。 |
Line 90: | Line 71: |
* Type B: *Mark、Enzo, 正田 * 光学テーブルのアクチュエーターが一部働いていないところがあるのが見つかった。ハイパワーコイルドライバーでテストする。 |
* IOO: *苔山 * 今日一日光を使う。 * Alignment: *和泉 * 今日の夕方、全員が出坑してからバッフルPDのチェック。 * 機器制御のチェック: *麻生、日立造船 |
Line 94: | Line 80: |
* Laser hazard * SRラインより奥。 |
* Laser hazard: IMMTより上流、夕方全員が出てからSR2-3ラインより奥。 |
Line 100: | Line 84: |
* 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 |
* Week of 1/29 * 1/29,30 leak check. * 1/31 Opening ETMY gate valve. * 1/31-2/2 Re-checking main beam to ETMY * Week of 2/5 * 2/5 Cooling start. |
Line 107: | Line 93: |
* 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * BSテーブルにPDを置けるかどうか。 * Eendの遮蔽板をいつ開けるか。 * 真空引きの最終確認。 |
* Issues * Network cableの整理 |
Line 124: | Line 106: |
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 131: | Line 118: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 138: | Line 125: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/30 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/31(Wed.)
- Remote participants by eZuce: Miyoki
- Report of work (*:responsible person)
- Vacuum: 木村
- Leakが三箇所でみつかった。一つは増し締めで解決。もう二つは高真空でのリークなので、今回はそのまま。
- 真空の判断でゲートバルブを開ける。
- Alignment: 宮川
- 1日の揺れが線形領域内の半分程度に収まった。Excitationが以前収まらない。
- Vacuum: 木村
- Work plan (*:responsible person)
- Vacuum: *木村、上田、宍戸、高橋
- 今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
- gate valveを開ける。
- IOO: *苔山
- 今日一日光を使う。
- Alignment: *和泉
- 今日の夕方、全員が出坑してからバッフルPDのチェック。
- 機器制御のチェック: *麻生、日立造船
- Vacuum: *木村、上田、宍戸、高橋
- Laser hazard: IMMTより上流、夕方全員が出てからSR2-3ラインより奥。
- Weekly
- Week of 1/29
- 1/29,30 leak check.
- 1/31 Opening ETMY gate valve.
- 1/31-2/2 Re-checking main beam to ETMY
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- Network cableの整理
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools