Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/2/5 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180206.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person |
Line 20: | Line 19: |
* ETMYアラインメント * 12/14 和泉、長野、川﨑 * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/14 * 12/15 * BS PDセット * 12/14 横澤 * 12/15 * 遮蔽板取り外し * 木村 |
* Beam leading to REFP port * *Izumi |
Line 67: | Line 54: |
2017/12/14(Thu.) | 2017/2/6(Tue.) |
Line 69: | Line 56: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by eZuce: Takahashi |
Line 72: | Line 58: |
* 遮蔽板取り外し: *木村、その他 * 朝から取り外し作業開始。終了次第宮川まで連絡。 |
* Report of work (*:responsible person) * Alignment and Vibration Isolation: Izumi, Okutomi * BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started. * IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi) * ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low. |
Line 75: | Line 64: |
* アラインメント: *和泉、長野、川崎、三代木 * ダンピング周りを見直している。PR3は0.2uradくらにまでなっている。 * 遮蔽板の取り外しが終わり次第アラインメント開始。 * ETMYのType A部分にモーターのスタックなどあるが、アラインメントには支障がなさそうなので、ETMYからの戻り光を確認するアラインメント作業は今日、明日で決行する。 |
* Work plan (*:responsible person) |
Line 80: | Line 66: |
* Type B: *Mark、Enzo, 正田, 和泉 * 昨日言っていたキーストーンが4mm低いというのはLVDTのキャリブレーションの間違い。実際にはキーストンの位置を1.5mm上げた。 * それでもダンピングはまだ効いていないようである。 * IMのコントロールをアップデートした。多少改善したが、いまやっと10uradくらいの揺れになったくらい。 |
* Alignment and Vibration Isolation: *Izumi * We can move moving masses of BF, or IPs of yaw to check TF can be recovered. * We will play one more day under vacuum. |
Line 85: | Line 70: |
* Type A: *牛場、宮本 * Fishing rodの稼働実験をした。結果は残念ながら動かなかった。 * さらに作業中に、別件として新たにモーターが端まで行ってしまってstuckしてしまった。 * unstuckできるのが最速で月曜日。月曜のフタ締めの準備中にやるか? * この問題は垂直方向のことなので、アラインメント作業には直接は影響なさそう。 |
* Type A: *Yokozawa * RT model of Type A will be separated into cryopayload and tower. * Type B * SR assembly continues. * Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area. * Weekly * Week of 2/5 * Finding causes of ETMY trouble. * Evacuation might be needed if ETMY is touching somewhere. * Cooling also will be delayed for 2weeks or so. |
Line 92: | Line 85: |
* PD設置: * 和泉君の指示で移動のタイミングを横澤君に知らせる。 * 時期としては今日の午後か、明日の午前くらい。 * Laser hazard * SRラインより奥。 * 明日の朝遮蔽板を落とすので、BS側でアルミ箔で塞いでおいて、しばらくはYend 1Fで作業が続けれるようにする。Yendの作業にめどがついたところでBSのアルミ箔をとってYend 1Fをハザードエリアにする。 * Weekly * 12/11の週 * メインビームの再アラインメント。 * ETMYからの戻り光確認。 * 12/13 昼休みに真空引きの前のミーティング。 * 12/18 EYC閉止。 * 12/18の週 * EYC閉止 * 問題点など * PR-BS相対位置測定後、EXでの再位置測定が必要か? * PR系のスリップが頻発している。特にPR3。 * WSのアカウントを個別にしてほしい。(和泉、その他) -> LDAPを入れなければならず、結構大変(山本、宮川) |
* Issues * IP drifted 2mm in the air, and another 2mm when pump down. |
Line 130: | Line 98: |
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 137: | Line 111: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 144: | Line 118: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/2/5 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/6(Tue.)
- Remote participants by eZuce: Takahashi
- Report of work (*:responsible person)
- Alignment and Vibration Isolation: Izumi, Okutomi
- BF yaw transfer function showed that it did not move well. It was fount that the position of IP was different from when pumping down started.
- IP drifted 2mm in the air, and another 2mm when pump down. (Takahashi)
- ETMY IPs were set back to where they were on 1/13. The transfer function now has the similar shape as before, but the Q of lowest peak is a bit low.
- Alignment and Vibration Isolation: Izumi, Okutomi
- Work plan (*:responsible person)
- Alignment and Vibration Isolation: *Izumi
- We can move moving masses of BF, or IPs of yaw to check TF can be recovered.
- We will play one more day under vacuum.
- Type A: *Yokozawa
- RT model of Type A will be separated into cryopayload and tower.
- Type B
- SR assembly continues.
- Alignment and Vibration Isolation: *Izumi
- Laser hazard: PSL. Green might be used late of the afternoon, then the center area and Y end will be the hazard area.
- Weekly
- Week of 2/5
- Finding causes of ETMY trouble.
- Evacuation might be needed if ETMY is touching somewhere.
- Cooling also will be delayed for 2weeks or so.
- Finding causes of ETMY trouble.
- Week of 2/5
- Issues
- IP drifted 2mm in the air, and another 2mm when pump down.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)